File #: 15-0243    Version: 1 Name:
Type: Report Status: Agenda Ready
File created: 2/24/2015 In control: Capital Investment Committee
On agenda: 3/4/2015 Final action:
Title: Stormwater Projects Status
Sponsors: Engineering
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DATE: March 4, 2015

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Paul Holzen, Director of Engineering

SUBJECT:
title
Stormwater Projects Status
body

Purpose
The purpose of this memo is to update the City of Franklin Board of Mayor and Aldermen (BOMA) on the current status of some of the City's stormwater projects.

Project Status

A. Jackson Lake Dredging Improvements
Key Dates: Design Start - 9/9/2008; Design Completion - June 2010; Bid Date - February 15, 2011; Construction Start - May 2, 2011; Construction Completion - March 2015*
*Denotes Estimated Dates
Cost: Design - $69,400.00; Construction - $1,663,931.73
Status Update: Actual dredging operations are complete. At this point, it has been determined that no additional sediment can be removed via hydraulic dredging operations. Approximately 13,000 CY of sediment has been removed. Contractor has not been able to remove the material through the winter months.

B. 100-Block Battle Avenue Drainage Improvements
Key Dates: Design Start - July 24, 2012 (BOMA Approved); Design Completion - July 2015*; Easement Acquisition Start - August 2015*; Easement Acquisition Completion - December 2015*; Bid Date - October 2015*; Construction Start - January 2016*; Construction Completion - July 2016*
*Denotes Estimated Dates
Cost: Initial Study - $46,500.00; Final Design - $131,700.00 (Including upcoming Amendment 1 of $68,200.00); Construction Estimate- $1,200,000.00
Status Update: The Board approved moving forward with the project on December 9, 2014. Design Amendment 1 for $68,200.00 will go to CIC in April for approval.

C. Figuers Drive and 400-Block Battle Avenue Drainage Improvements
Key Dates: Design Start - November 26, 2013 (BOMA Approved); Design Completion for Preliminary Design- November 2014; Easement Acquisition Start - TBD; Easement Acquisition Completion - TBD; Bid Date - TBD; Constru...

Click here for full text