File #: 15-0487    Version: 1 Name:
Type: Report Status: Passed
File created: 5/11/2015 In control: Capital Investment Committee
On agenda: Final action: 5/28/2015
Title: Stormwater Projects Status Report
Sponsors: Engineering

DATE: May 28, 2015

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineering/CIP Executive
Paul Holzen, Director of Engineering

SUBJECT:
title
Stormwater Projects Status Report
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's stormwater projects.

Project Status
A. Jackson Lake Dredging Improvements
Key Dates: Design Start - 9/9/2008; Design Completion - June 2010; Bid Date - February 15, 2011; Construction Start - May 2, 2011; Construction Completion - Summer 2015*
*Denotes Estimated Dates
Cost: Design - $69,400.00; Construction - $1,663,931.73
Status Update: Actual dredging operations are complete. At this point, it has been determined that no additional sediment can be removed via hydraulic dredging operations. Approximately 13,000 CY of sediment has been removed. Contractor has been instructed to have all work complete by July 2015.

B. 100-Block Battle Avenue Drainage Improvements
Key Dates: Design Start - July 24, 2012 (BOMA Approved); Design Completion - August 2015*; Easement Acquisition Start - August 2015*; Easement Acquisition Completion - December 2015*; Bid Date - January 2016*; Construction Start - March 2016*; Construction Completion - August 2016*
*Denotes Estimated Dates
Cost: Initial Study - $46,500.00; Final Design - $131,700.00 (Including Amendment 1 of $68,200.00); Construction Estimate- $1,200,000.00
Status Update: The BOMA approved moving forward with the project on December 9, 2014. Amendment No. 1 to the design contract (COF Contract No. 2013-0180) was approved at the April 28TH BOMA meeting. This amendment allows for completion of final design.

C. Figuers Drive and 400-Block Battle Avenue Drainage Improvements
Key Dates: Design Start - November 26, 2013 (BOMA Approved); Design Completion for Preliminary Design- November 2014...

Click here for full text