FRANKLIN PARK SUBDIVISION, SITE PLAN, (OPEN SPACE LOT/PARKLAND/INFRASTRUCTURE)
Perf agreement: Drainage $166,000
Established: November 9, 2012
Previous Action: 6/25/13 PA posted
6/20/14 Approved extension to 12/12/14
12/12/14 Reduction denied; extend to 12/11/15
3/20/15 Release denied, but reduce 75% from $664,000; extend to 3/18/16
3/18/16 Extend to 3/17/17
Recommendation: Extend to February 22, 2018.
Reason/Deficiency: The sidewalk shall be constructed with pervious concrete, per the approved drainage plan. Contact the inspector to schedule a meeting onsite to discuss the rest of punchlist. Drainage as-builts shall be revised, as necessary following completion of the punchlist, and resubmitted with the next release request.