File #: 16-0109    Version: 1 Name:
Type: Report Status: Agenda Ready
File created: 1/14/2016 In control: Capital Investment Committee
On agenda: 1/28/2016 Final action:
Title: Transportation Projects Status Report
Sponsors: Engineering

DATE: January 28, 2016

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, Director of Engineering


SUBJECT:
title
Transportation Projects Status Report
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's transportation projects.

Project Status
A. Mack Hatcher Parkway NW Extension
BOMA Priority Ranking: N/A (Highest Priority)
Key Dates: Design Start - August 14, 2007 (BOMA Approval); Re-Design Completion - January 2015; ROW Start - December 2009; ROW Completion - June 2012; Construction Start - Currently Not Funded; Construction Completion - Currently Not Funded
Cost: Design - $3,502,501; ROW - $13,397,520 (Provided by TDOT); Construction - $58,700,000 (Provided by TDOT)
Status Update: TDOT has agreed to build the full intersections at SR96, Hillsboro Road and Del Rio Pike as a part of the 2-lane Mack Hatcher Parkway construction. On Thursday, April 9TH, the City received notification from the TDOT Communications Office of projects on the Statewide Transportation Improvement Plan (STIP) for the 3-year period from 2016-2018, and this project was not included. On December 9TH, the Nashville Area Metropolitan Planning Organization (MPO) release its draft 2040 Regional Transportation Plan (RTP). Being listed in this plan is the first step for transportation projects to receive federal funding. The Mack Hatcher Parkway NW Extension is listed as one of the short term projects for funding. Ultimately though, the decision to proceed with construction lies with TDOT.

B. Hillsboro Road Improvements Phase 2 (Independence Square to Mack Hatcher Pkwy)
BOMA Priority Ranking: #1
Key Dates: Design Start - March 24, 2008 (BOMA Approval); Design Completion - March 2015; ROW Start - March 2013; ROW Completion - May 2015; Bid Date - January 2016*; Construction Start - March 2016*; Construction Com...