DATE:                                                               July 23, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          David Parker, City Engineer/CIP Executive

                                          Paul Holzen, Director of Engineering

                                          Jonathan Marston, Staff Engineer 3                     

                                          

SUBJECT:                                          

title

Consideration of Resolution 2015-45, A Resolution Awarding the Construction Contract (COF Contract No. 2014-0042) for the Century-Beasley Connector Project to Jenco Construction, Inc. in the amount of $399,250.97 (07/23/15 CIC 4-0) 

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning DRAFT Resolution 2015-45 to award the construction contract for the Century-Beasley Connector Project to Jenco Construction, Inc.

 

Background

The Century-Beasley Connector Project has been identified as a priority project in the Capital Investment Plan, and generally includes the construction of approximately 500 linear feet of new roadway with curb and gutter, storm infrastructure, and utility coordination.  The estimated project cost was $457,000.

 

On July 8, 2015, the City received sealed bids for the construction of this project and publicly read them aloud.  Jenco Construction, Inc., with a bid amount of $399,250.97, was the apparent low bidder.

 

Financial Impact

Funding for this project will come from the Capital General Obligation Bonds.

 

Recommendation

rec

Staff recommends approval of DRAFT Resolution 2015-45, which awards the construction contract (COF Contract No. 2015-0042) for the construction of the Century-Beasley Connector Project to Jenco Construction, Inc. in the amount of $399,250.97.