SILVER GRACE PUD SUBDIVISION, SITE PLAN, SECTION 1
Perf agreement: Landscaping Phase B $58,000
Established: August 26, 2010
Previous Action: FMPC reapproved 11/18/10 to add one unit; landscaping revised again 2/24/11.
5/26/11 PA posted
5/18/12 Approved extension to 5/17/13
5/17/13 Approved extension to 5/16/14
5/16/14 Extend to 5/15/15 (Re-phased; this is Phase B, same amount).
Recommendation: Approved extension to May 26, 2016. This site is still under construction.
Perf agreement: Landscaping Phase C $35,000
Established: August 26, 2010
Previous Action: FMPC reapproved 11/18/10 to add one unit; landscaping revised again 2/24/11.
5/26/11 PA posted
5/18/12 Approved extension to 5/17/13
5/17/13 Approved extension to 5/16/14
5/16/14 Extend to 5/15/15 (Re-phased; this is Phase C, new original amount $35,000).
Recommendation: Approved extension to May 26, 2016. This site is still under construction.
Maint agreement: Landscaping Phase A $73,000
Established: May 16, 2014
Previous Action: FMPC reapproved 11/18/10 to add one unit; landscaping revised again 2/24/11.
5/26/11 PA posted
5/18/12 Approved extension to 5/17/13
5/17/13 Approved extension to 5/16/14
5/16/14 Release PA, establish MA for $73,000 (Re-phased; this is Phase A, new original amount $291,000).
6/10/14 MA posted
Recommendation: Extend to May 26, 2016.
Reason/Deficiency: The two missing River Birch in the islands along the west side of the building shall be installed. The stressed Cryptomeria Japonica in the western buffer shall be monitored, and if they do not survive, they shall be replaced.