File #: 16-0415    Version: 1 Name:
Type: Report Status: Passed
File created: 4/25/2016 In control: Capital Investment Committee
On agenda: 4/28/2016 Final action: 4/28/2016
Title: Stormwater Projects Status Report

DATE: April 25, 2016

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, Director of Engineering

SUBJECT:
title
Stormwater Projects Status Report
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's stormwater projects.

Project Status

A. 100-Block Battle Avenue Drainage Improvements
Key Dates: Design Start - July 24, 2012 (BOMA Approved); Design Completion - January 2016*; Easement Acquisition Start - June 2016*; Easement Acquisition Completion - November 2016*; Bid Date - January 2017*; Construction Start - April 2017*; Construction Completion - August 2017*
*Denotes Estimated Dates
Cost: Initial Study - $46,500.00; Final Design - $131,700.00 (Including Amendment 1 of $68,200.00); Construction Estimate- $1,200,000.00
Status Update: The BOMA approved moving forward with the project on December 9, 2014. Amendment No. 1 to the design contract (COF Contract No. 2013-0180) was approved at the April 28TH BOMA meeting. This amendment allows for completion of final design. Updated survey completed in July. Geotechnical explorations were completed at the end of September. The final design will continue into spring 2016. ROW Acquisition could begin in early summer 2016. Staff and the design consultant are currently evaluating design changes based upon the recent geotechnical data. The depth of bedrock could hamper the depth of the proposed detention pond.

B. Figuers Drive and 400-Block Battle Avenue Drainage Improvements
Key Dates: Design Start - November 26, 2013 (BOMA Approved); Design Completion for Preliminary Design- November 2014; Easement Acquisition Start - TBD; Easement Acquisition Completion - TBD; Bid Date - TBD; Construction Start - TBD; Construction Completion - TBD;
Cost: Initial Design - $82,000.00; Final Design - $125,200.00; Construction - TBD (engineering estim...

Click here for full text