EDDY LANE INDUSTRIAL OFFICE SUBDIVISION, SITE PLAN
Perf agreement: Landscaping Phase 1B $81,000
Established: May 24, 2012
Previous Action: 9/4/12 PA posted
10/18/13 Approved extension to 10/17/14
10/17/14 Approved extension to 10/16/15
10/22/15 Approved extension to 10/27/16; additional phases not started yet.
Recommendation: Approved extension to October 26, 2017. This site is still under construction. Installation is intended to be completed with construction of the next structure.
Maint agreement: Landscaping Phase 1A $20,000
Established: May 16, 2014
Previous Action: 9/4/12 PA posted
10/18/13 Reduce from $78,000; extend to 10/17/14
11/8/13 Extend to 11/14/14
5/16/14 Release PA, establish MA for $20,000
6/10/14 MA posted
5/15/15 Extend to 5/20/16
5/26/16 Extend to 5/25/17
Recommendation: Extend to October 26, 2017.
Reason/Deficiency: The dead tree on the southern side of the detention area shall be replaced. Many of the required plantings at the northern detention area are missing and shall be replaced.