SPRING CREEK SUBDIVISION, SITE PLAN, SECTION 1, REVISION 4 (SPRING CREEK CENTER)
Perf agreement: Landscaping (Retail) $77,000
Established: April 22, 2010
Previous Action: 4/22/10 Reapproved by FMPC
8/18/10 PA posted
6/17/11 Extend to 6/15/12
6/15/12 Approved extension to 6/21/13
6/21/13 Extend to 6/20/14
6/26/14 Reduce from $102,000; extend to 6/25/15
6/25/15 Approved extension to 6/23/16
6/23/16 Extend to 6/22/17; still under construction
6/22/17 Extend to 6/28/18
Recommendation: Approved extension to June 27, 2019.