File #: 14-584    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 10/31/2014 In control: Board of Mayor & Aldermen
On agenda: 11/25/2014 Final action: 11/25/2014
Title: Consideration of Amendment No. 1 to the Professional Services Agreement (COF Contract 2013-0034) with CDM Smith, Inc for the Mack Hatcher Extension Project [SR-397 Mack Hatcher Parkway West, From South of SR-96, West of Franklin to East of SR-106 (US-431) North of Franklin Williamson County] For a Not-to-Exceed amount of $355,056. (11/12/14 CIC 3-0).
Sponsors: David Parker
Attachments: 1. COF 2013-0034 Mack Hatcher Amendment 1 - scope Exhibit A, 2. COF 2013-0034 Mack Hatcher Amendment 1 - PSA.pdf

DATE: October 31, 2014

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, P.E, City Engineer/CIP Executive
Paul P. Holzen, P.E., Director of Engineering


SUBJECT:
title
Consideration of Amendment No. 1 to the Professional Services Agreement (COF Contract 2013-0034) with CDM Smith, Inc for the Mack Hatcher Extension Project [SR-397 Mack Hatcher Parkway West, From South of SR-96, West of Franklin to East of SR-106 (US-431) North of Franklin Williamson County] For a Not-to-Exceed amount of $355,056. (11/12/14 CIC 3-0).
body

Purpose
The purpose of this memorandum is to bring forward a new Professional Services Agreement with CDM Smith, Inc for the re-design of the Mack Hatcher Parkway Extension Project.

Background
Final roadway and construction plans where submitted to TDOT on May 6, 2011 to finalize the design of the Mack Hatcher Parkway Extension project. Since that time TDOT has requested numerous meeting to discuss the intersection designs at SR96 and Del Rio Pike, landscaping design, haul road and temporary bridge access, pavement re-design and the requirement to updated our erosion prevention and sediment control plans per TDEC's new General Permit (issued May 23, 2011). On March 19, 2013 the City of Franklin received a letter from Paul Degges, TDOT Deputy Commissioner and Chief Engineer requesting the City to revise and resubmit plans to reflect re-design of the roundabouts at SR96 and Del Rio Pike to signalized intersections. This work was completed at a cost of $277,500. TDOT is now asking the City to redesign the project as a two lane arterial roadway. The additional cost as negotiated with TDOT, City and CDM Smith, Inc is for an amount not to exceed $355,056.

Below is a summary of the historical contact cost and amendments associated with the design:
6/14/2007 BOMA approved an agreement with CDM Smith, Inc (Formally known as WilburSmith Associates) for preliminary desi...

Click here for full text