File #: 14-686    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 11/19/2014 In control: Board of Mayor & Aldermen
On agenda: 1/13/2015 Final action: 1/13/2015
Title: Consideration of an Agreement of Sale (COF Contract 2014-0305) for Right of Way with Williamson County Schools in the amount of $14,850.00 and an Agreement of Sale (COF Contract 2014-0327) for Easements with Williamson County Schools in the amount of $63,550.00 on the Franklin High Property for the Hillsboro Road Improvements Project. (12/09/14 WS) Purpose The purpose of this memo is to give the Board of Mayor and Alderman information regarding the purchase of required Right of Way and Easements for the Hillsboro Road Improvements project. Background On October 21st, 2014, staff met with Mr. Kevin Fortney, Facilities Manager for the Williamson County Schools, to discuss and make an offer to purchase the required Right of Way and Easements for the Hillsboro Road Improvements project. An appraisal completed by B.G. Jones and a review appraisal completed by Standifer and Associates valued the State Right of Way at $14,850.00 and the City of Franklin easements at $63,550.00. At ...
Sponsors: David Parker, Paul Holzen
Attachments: 1. COF 2014-0305 and COF 2014-0327 - Agreement of Sale WCSD
DATE:                  November 19, 2014
 
TO:            Board of Mayor and Aldermen
 
FROM:            Eric Stuckey, City Administrator
            David Parker, City Engineer
            Paul Holzen, Director of Engineer
            Ben Worley, Right of Way Agent
                  
SUBJECT:            
title
Consideration of an Agreement of Sale (COF Contract 2014-0305) for Right of Way with Williamson County Schools in the amount of $14,850.00 and an Agreement of Sale (COF Contract 2014-0327) for Easements with Williamson County Schools in the amount of $63,550.00 on the Franklin High Property for the Hillsboro Road Improvements Project. (12/09/14 WS)  
 
Purpose
The purpose of this memo is to give the Board of Mayor and Alderman information regarding the purchase of required Right of Way and Easements for the Hillsboro Road Improvements project.
 
Background
On October 21st, 2014, staff met with Mr. Kevin Fortney, Facilities Manager for the Williamson County Schools, to discuss and make an offer to purchase the required Right of Way and Easements for the Hillsboro Road Improvements project. An appraisal completed by B.G. Jones and a review appraisal completed by Standifer and Associates valued the State Right of Way at $14,850.00 and the City of Franklin easements at $63,550.00.  At this time Williamson County Schools is also taking this item to the School Board for consideration.
 
Financial Impact
The purchase price as appraised is $14,850.00 for the State Right of Way and $63,550.00 for the City of Franklin Easements.  These costs are incorporated in the project budget for the Hillsboro Road, Phase 2 project.
 
Recommendation
Staff recommends approval of COF Contract 2014-0305 and COF Contract 2014-0327.