File #: 15-0242    Version: 1 Name:
Type: Report Status: Agenda Ready
File created: 2/24/2015 In control: Capital Investment Committee
On agenda: 3/4/2015 Final action:
Title: Water & Sewer Projects Status
Sponsors: Engineering
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DATE: March 4, 2015

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineering/CIP Executive
Mark Hilty, Director of Water Management
Paul Holzen, Director of Engineering

SUBJECT:
title
Water & Sewer Projects Status
body

Purpose
The purpose of this memo is to update the City of Franklin Board of Mayor and Aldermen (BOMA) on the current status of some of the City's water and sewer projects.

Project Status

A. 11th Avenue Improvements
Key Dates: Design Start - January 22, 2013; Design Completion - July 2013; Easement Acquisition Start - November 2013; Easement Acquisition Completion - January 2014; Bid Date: November 25, 2013; Construction Start - May 2014; Construction Completion - November 2014
Cost: Design - $47,232.00; Construction - $679,558.00
Funding Source: Design - Water and Sewer Operating; Construction - Water & Sewer Fund
Status Update: All major work is complete (water, sewer, sidewalks and paving). There will be some of the sidewalks that will need to be replaced now that the paving is complete. Staff met with the contractor onsite on January 28, 2015 to discuss.

B. Spencer Creek Basin - South Prong Interceptor Upgrade
Key Dates: Design Start - April 23, 2013; Design Completion - June 2015; Bid Date: Not Funded; Construction Start - Not Funded; Construction Completion - Not Funded
Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded
Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD
Status Update: The final Technical Memorandum was submitted on May 15, 2014. Design plans are currently in the works but the project will not be constructed until the monies are available from the WMD budget.

C. Charlton Green Sanitary Sewer Improvements
Key Dates: Design Start - November 12, 2013; Design Completion - March 2014; Bid Date: April 7, 2014; Construction Start - December 1, 2014; Construction Completion...

Click here for full text