File #: 16-0461    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 5/13/2016 In control: Board of Mayor & Aldermen
On agenda: 6/14/2016 Final action: 6/14/2016
Title: Consideration of Change Order No. 1 to the Construction Contract (COF Contract No. 2014-0037, Resolution 2015-46) with Jones Bros. Contractors, LLC for the 3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase I, TDOT PIN 109424.00) (05/26/16 CIC 4-0)
Attachments: 1. COF2014-0037_3rd_Ave_Trail-Change_Order_1_ExhA

DATE: May 13, 2016

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Paul Holzen, Director of Engineering
William Banks, Staff Engineer



SUBJECT:
title
Consideration of Change Order No. 1 to the Construction Contract (COF Contract No. 2014-0037, Resolution 2015-46) with Jones Bros. Contractors, LLC for the 3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase I, TDOT PIN 109424.00) (05/26/16 CIC 4-0)
body

Purpose
The purpose of this memorandum is to provide information to the City of Franklin Board of Mayor and Aldermen (BOMA) concerning Change Order No. 1 to the construction contract (COF Contract No. 2014-0037, Resolution 2015-46) with Jones Bros. Contractors, LLC for the 3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase I, TDOT PIN 109424.00).

Background
The 3rd Avenue North Trail/Greenway (Bicentennial Park Phase I) construction contract was awarded by BOMA to Jones Bros. Contractors, LLC on August 11, 2015, in the amount of $1,253,257.31. The original contract completion date was scheduled for May 17, 2016 (240 Calendar Days).

This Change Order No. 1 includes small changes required to properly complete the project, and a request for additional time to the construction contract. Change Order No. 1 details include the following:
1. Additional pay items:
a. Tree removal to eliminate a conflict with overlook installation.
b. Storm drainage structures to tie into the 3rd Ave N Roadway Project's storm system.
c. Surge stone required for compaction around water stairs and under the overlook structure to prevent area from washing out when river level rises. Also, the existing excavated soil did not meet specifications for backfill placement, so it could not be re-used as indicated on the plans.
2. Modify contract time as follows:
a. 10 additional calendar days due to normal weather delays/impacts (rain, snow, etc.) from September 2015 thru April 2016.
b...

Click here for full text