COOL SPRINGS LIFE SCIENCE CENTER SUBDIVISION, SITE PLAN
Perf agreement: Stormwater drainage/detention $27,000
Established: August 15, 2002
Previous Action: 7/2/04 PA posted
7/15/04 FMPC approval extended to 12/15/04
10/14/05 Approved extension to 7/27/06
7/27/06 Approved extension to 1/25/07
1/25/07 Approved extension to 1/24/08
1/24/08 Approved extension to 1/22/09
1/22/09 Approved extension to 1/28/10
1/28/10 Approved extension to 1/27/11
1/27/11 Extend to 1/26/12
1/26/12 Approved extension to 1/24/13
1/24/13 Approved extension to 1/23/14
1/23/14 Approved extension to 1/22/15
1/22/15 Extend to 1/28/16
1/28/16 Approved extension to 1/26/17; third building not started yet.
Recommendation: Extend to July 27, 2017.
Reason/Deficiency: The final topcoat of asphalt is required to be applied prior to release of performance. The structure between C4 and C5 shall be located and exposed.