File #: 15-0658    Version: 1 Name:
Type: Report Status: Passed
File created: 7/13/2015 In control: Capital Investment Committee
On agenda: 7/23/2015 Final action: 7/23/2015
Title: Water and Sewer Projects Status Report
Sponsors: Engineering

DATE: July 23, 2015

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Paul Holzen, Director of Engineering

SUBJECT:
title
Water and Sewer Projects Status Report
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's water and sewer projects.

Project Status
rec

A. Spencer Creek Basin - South Prong Interceptor Upgrade
Key Dates: Design Start - April 23, 2013; Design Completion - June 2015*; Bid Date: Not Funded; Construction Start - Not Funded; Construction Completion - Not Funded
*Denotes Estimated Date
Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded
Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD
Status Update: Design plans are currently underway and are approximately 50% complete. Staff and the engineer met in the field to discuss how to route the sewer through Aspen Grove Park. The project will not be constructed until funding is available from the Water Management Department budget.

B. Charlton Green Sanitary Sewer Improvements
Key Dates: Design Start - November 12, 2013; Design Completion - March 2014; Bid Date: April 7, 2014; Construction Start - December 1, 2014; Construction Completion - April 2015
Cost: Design - $19,895.00; Easement - $3,500.00; Construction -$465,304.90
Funding Source: Design -Sewer Operating; Construction - Sewer Fund
Status Update: The final change order is on the July 2015 Board of Mayor and Aldermen meeting agenda for approval.

C. Spencer Creek at Franklin Road Sewer
Key Dates: Design Start - March 11, 2014; Design Completion - June 2015; Easement Acquisition Start - July 2015*; Easement Acquisition Completion - September 2015*; Bid Date: October 2015*; Construction Start - December 2015*; Construction Completion - May 2016*
*Denotes Estimated Date
...

Click here for full text