DATE: April 27, 2017
TO: Board of Mayor and Aldermen
FROM: Eric Stuckey, City Administrator
Paul Holzen, City Engineer/Director of Engineering
Jonathan Marston, Assistant Director of Engineering
William Banks, Staff Engineer
SUBJECT:
title
Consideration of Change Order No. 1 to the Construction Contract (COF Contract No. 2015-0002, TDOT PIN 108409.00) with Eutaw Construction Company, Inc. for the Hillsboro Road Improvements Project Phase 2, Independence Square to Mack Hatcher Parkway
body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Change Order No. 1 to the construction contract (COF Contract No. 2015-0002, TDOT PIN 108409.00) with Eutaw Construction Company, Inc. for the Hillsboro Road Improvements Project Phase 2, Independence Square to Mack Hatcher Parkway.
Background
The Hillsboro Road Improvements Project Phase 2 construction contract was awarded by BOMA to Eutaw Construction Company, Inc. on March 8, 2016, in the amount of $11,995,005.13. The construction contract time started on April 18, 2016, with a contract completion date of June 21, 2017 (430 Calendar Days).
The proposed Change Order No. 1 details include the following:
1. To add 154 calendar days to the original contract time due to utility conflicts and additional items of work. New contract completion date will be November 22, 2017 (584 total calendar days).
2. Addition of pay item to adjust existing valve boxes for water line to include the cost of riser rings.
3. Addition of pay item for Type A Warning Lights to be used for traffic control and safety.
4. Addition of pay item to use Fixture Type A (LED) for street lighting and removing items Fixture Type A (Metal Halide) and Fixture Type B (Metal Halide) resulting in no additional cost to the contract.
5. Addition of pay item for Portable Barrier Rail Delineators to be used for traffic control and safety.
6. Removal of pay item for Vertical Pa...