File #: 20-0097    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 1/15/2020 In control: Capital Investment Committee
On agenda: 1/23/2020 Final action: 1/23/2020
Title: Consideration Of A DRAFT Professional Services Agreement (COF Contract No. 2019-0372) With Alfred Benesch & Company For The Design Of The Bridge Replacement On Pratt Lane Over Five Mile Creek In An Amount Not-To-Exceed $94,125.00.
Sponsors: Engineering
Attachments: 1. Contract_2019_0372_PSA_Benesch_DESIGN_PrattLaneBridge.pdf.pdf, 2. Contract_2019_0372_PSAScope_Benesch_DESIGN_PrattLaneBridge.pdf

 

DATE:                                                               January 15, 2020

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, City Engineer/Director of Engineering

                                          Jonathan Marston, Assistant Director of Engineering                     

                                          

SUBJECT:                                          

title

Consideration Of A DRAFT Professional Services Agreement (COF Contract No. 2019-0372) With Alfred Benesch & Company For The Design Of The Bridge Replacement On Pratt Lane Over Five Mile Creek In An Amount Not-To-Exceed $94,125.00. 

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning a Professional Services Agreement (PSA) with Alfred Benesch & Company (Benesch) for the design of the bridge replacement on Pratt Lane over Five Mile Creek.

 

Background

In October 2015, City staff, Boyle Investment Company (Boyle) and the Lampo Group negotiated the required on-site and off-site improvements associated with the development of the Lampo Group Corporate Headquarters (i.e. Ramsey Solutions), which is located within the Reams-Fleming Tract of Berry Farms.  During those negotiations, the City agreed to be responsible for all necessary roadway and bridge improvements to Pratt Lane.  On August 13, 2019, the BOMA approved Resolution 2019-68 to adopt the project list for the fiscal years (FYs) 2019-2028 Capital Investment Program (CIP).  Included in that project list was the Pratt Lane Bridge Replacement project at an estimated total cost of $1,500,000.

 

This PSA with Benesch will provide the final design plans for the replacement bridge and roadway modifications to accommodate the bridge.

 

Financial Impact

The total cost of this PSA is $94,125.00.  The funding for project expenses is tentatively programmed to come from the General Fund.  This corresponds to a General Ledger (GL) code of 110-89450-43100.

 

Recommendation

rec

Staff recommends approval of the PSA (COF Contract No. 2019-0372) with Alfred Benesch & Company in an amount not-to-exceed $94,125.00.