File #: 15-0102    Version: 1 Name:
Type: Planning Item Status: Passed
File created: 1/12/2015 In control: Franklin Municipal Planning Commission
On agenda: 1/22/2015 Final action: 1/22/2015
Title: Cool Springs Life Science Center Subdivision, site plan; extend the performance agreement for stormwater drainage/detention improvements. (CONSENT AGENDA)
COOL SPRINGS LIFE SCIENCE CENTER SUBDIVISION, SITE PLAN
Perf agreement:      Stormwater drainage/detention $27,000      
Established:      August 15, 2002
Previous Action:      7/2/04 PA posted
7/15/04 FMPC approval extended to 12/15/04
10/14/05 Approved extension to 7/27/06
7/27/06 Approved extension to 1/25/07
1/25/07 Approved extension to 1/24/08
1/24/08 Approved extension to 1/22/09
1/22/09 Approved extension to 1/28/10
1/28/10 Approved extension to 1/27/11
1/27/11 Extend to 1/26/12
1/26/12 Approved extension to 1/24/13
1/24/13 Approved extension to 1/23/14
1/23/14 Approved extension to 1/22/15; 3rd building not started.
Recommendation:      Extend to January 28, 2016.  Construction has not begun on the third building yet.