HURSTBOURNE PARK PUD SUBDIVISION, SITE PLAN, SECTIONS 1-3
Maint agreement: Landscaping (section 1) $55,000
Established: May 16, 2014
Previous Action: 3/19/07 PA posted
1/11/08 Reduction denied; extend to 1/22/09
1/16/09 Reduce from $218,000; extend to 1/15/10
1/15/10 Extend to 1/21/11; still under construction
1/27/11 Extend to 1/26/12
1/26/12 Extend to 1/24/13
1/24/13 Extend to 1/23/14
1/23/14 Approved extension to 1/22/15
5/16/14 Release PA, establish MA for $55,000
5/27/14 MA posted
5/28/15 Extend to 5/26/16
5/26/16 Extend to 5/25/17
Recommendation: Release the maintenance agreement.
Perf agreement: Landscaping (section 3) $76,000
Established: July 27, 2006
Previous Action: Post before section 3 is platted
8/18/14 PA posted
6/25/15 Extend to 6/23/16; still under construction.
Recommendation: Extend to June 22, 2017. This section is still under construction.