File #: 15-0172    Version: 1 Name:
Type: Contract/Agreement Status: Agenda Ready
File created: 1/28/2015 In control: Capital Investment Committee
On agenda: 2/5/2015 Final action:
Title: Stormwater Projects Status
Sponsors: Engineering
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DATE: February 5, 2015

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Paul Holzen, Director of Engineering

SUBJECT:
title
Stormwater Projects Status
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's stormwater projects.

Project Status
A. Jackson Lake Dredging Improvements
Key Dates: Design Start - 9/9/2008; Design Completion - June 2010; Bid Date - February 15, 2011; Construction Start - May 2, 2011; Construction Completion - March 2015(Estimated)
Cost: Design - $69,400.00; Construction - $1,663,931.73
Status Update: Actual dredging operations are complete. At this point, it has been determined that no additional sediment can be removed via hydraulic dredging operations. Approximately 13,000 CY of sediment has been removed. Contractor is working to remove dried sediment and restore the neighboring staging area.

B. 100-Block Battle Avenue Drainage Improvements
Key Dates: Design Start - July 24, 2012 (BOMA Approved); Design Completion for Drainage Study- May 2013 (Estimated); Easement Acquisition Start - October 2015 (Estimated); Easement Acquisition Completion - December 2014 (Estimated); Bid Date - January 2015 (Estimated); Construction Start - March 2015 (Estimated); Construction Completion - July 2015 (Estimated);
Cost: Initial Study - $46,500.00; Final Design - $63,500.00; Construction - $600,000.00 (engineering estimate)
Status Update: The Board approved moving forward with the project on December 9, 2014. City is currently negotiating with Neel-Schaffer on PSA amendment items, which will allow the project design to be completed. ROW Acquisition could begin as soon as late Spring.

C. Figuers Drive and 400-Block Battle Avenue Drainage Improvements
Key Dates: Design Start - November 26, 2013 (BOMA Approved); Design Completion for P...