RIZER POINT PUD SUBDIVISION, SITE PLAN, SECTION 1
Perf agreement: Sidewalks $8,750
Established: August 15, 2012
Previous Action: 8/21/13 PA posted
7/18/14 Reduce 75% from $35,000; extend to 7/17/15
7/17/15 Extend to 7/15/16
3/18/16 Release denied; extend to 3/17/17; not complete.
Recommendation: Extend to March 22, 2018.
Maint agreement: Streets $27,100
Established: March 18, 2016
Previous Action: 8/16/13 Reduce 75%+ from $271,000; extend to 8/15/14
8/21/13 PA posted
8/15/14 Extend to 8/21/15
8/21/15 Extend to 8/19/16
3/18/16 Release PA, establish MA for $27,100
3/30/16 MA posted
Recommendation: Extend to March 22, 2018.
Reason/Deficiency: Thermoplastic stop bars shall be installed, as discussed with the inspector.