File #: 15-0866    Version: 1 Name:
Type: Report Status: Agenda Ready
File created: 9/12/2015 In control: Capital Investment Committee
On agenda: 9/24/2015 Final action:
Title: Water and Sewer Projects Status Report
Sponsors: Engineering
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

DATE: September 24, 2015

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Mark Hilty, Director of Water Management
Paul Holzen, Director of Engineering

SUBJECT:
title
Water and Sewer Projects Status Report
body

Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's water and sewer projects.

Project Status
A. Spencer Creek Basin - South Prong Interceptor Upgrade
Key Dates: Design Start - April 23, 2013; Design Completion - October 2015*; Bid Date: Not Funded; Construction Start - Not Funded; Construction Completion - Not Funded
*Denotes Estimated Date
Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded
Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD
Status Update: Design plans are still being developed and are approximately 50% complete. The project will not be constructed until funding is available from the Water Management Department budget.

B. Spencer Creek at Franklin Road Sewer
Key Dates: Design Start - March 11, 2014; Design Completion - June 2015; Easement Acquisition Start - September 2015*; Easement Acquisition Completion - November 2015*; Bid Date: January 2016*; Construction Start - March 2016*; Construction Completion - September 2016*
*Denotes Estimated Date
Cost: Design - $40,000.00; Easement - TBD; Construction - TBD
Funding Source: Design - Sewer Fund
Status Update: The plans are 100% complete. Easement acquisition will begin after the appraisals are completed.

C. Curd Branch and Watson Branch Interceptor Sewer
Key Dates: Design Start - February 25, 2014; Design Completion - March 2015; Easement Acquisition Start - February 2015; Easement Acquisition Completion - September 2015*; Bid Date: October 2015*; Construction Start - December 2015*; Construction Completion - December 2...

Click here for full text