WESTHAVEN PUD SUBDIVISION, SITE PLAN, SECTION 10
Maint agreement: Landscaping (Phase 2) $3,000
Established: April 23, 2015
Previous Action: 4/23/09 FMPC split landscaping into two phases to allow built portion to go to maintenance. This is Phase 2.
4/22/10 Approved extension to 4/28/11; still under construction.
4/28/11 Extend to 4/26/12
4/26/12 Approved extension to 4/25/13
4/25/13 Extend to 4/24/14; still under construction
4/24/14 Extend to 4/23/15
4/23/15 Release PA, establish MA for $3,000
6/15/15 MA posted
Recommendation: Release the maintenance agreement.