File #: 15-0585    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 6/15/2015 In control: Work Session
On agenda: 8/25/2015 Final action: 8/25/2015
Title: *Consideration of a Utility Relocation Agreement (COF Contract No. 2015-0044) with AT&T Tennessee for the Hillsboro Road Improvements Project Phase 2, from Independence Square to Mack Hatcher Parkway, in the estimated amount of $140,130.60 (06-25-15 CIC; Deferred from 7/14/15 BOMA; 08/25/15 WS)
Sponsors: Engineering
Attachments: 1. COF 2015-0044 HillsboroPh2 ATT Signed

DATE: June 25, 2015

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Paul Holzen, Director of Engineering
William Banks, Staff Engineer 1

SUBJECT:
title
*Consideration of a Utility Relocation Agreement (COF Contract No. 2015-0044) with AT&T Tennessee for the Hillsboro Road Improvements Project Phase 2, from Independence Square to Mack Hatcher Parkway, in the estimated amount of $140,130.60 (06-25-15 CIC; Deferred from 7/14/15 BOMA; 08/25/15 WS)
body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning a utility relocation agreement (COF Contract No. 2015-0044) with AT&T Tennessee for the Hillsboro Road Improvements Project Phase 2, from Independence Square to Mack Hatcher Parkway.

Background
During development of the final construction plans for Hillsboro Road Phase 2, multiple utility coordination meetings with AT&T were held. Because the City is undergrounding all overhead utilities to new buried duct bank systems, AT&T's local phone service distribution plans had to be designed (by the City) and incorporated into the Hillsboro Road design plans. But, AT&T has a separate existing underground fiber optic system that needs relocating as well during the construction of Hillsboro Road. This separate AT&T fiber optic system is the responsibility of AT&T, and therefore was designed by AT&T's own consultants.

Per this utility relocation agreement, it is in the mutual interest of both the City and AT&T that the AT&T fiber optic utility relocation work be performed as part of the City's upcoming Hillsboro Road Phase 2 Project's construction contract, COF Contract No. 2015-0002. The City will show the proposed relocation of the AT&T facilities in the Hillsboro Road Phase 2 Project construction plans as project cost items. The City will be responsible for having its contractor perform the AT&T u...

Click here for full text