SEWARD HALL SUBDIVISION, SITE PLAN, LOT 1 (BETHEL COMMUNITY CHURCH)
Perf agreement: Landscaping Phase 3 $27,000
Established: January 26, 2006
Previous Action: 1/29/10 This site split into 3 phases; this is Phase 3, new original amount $27,000; extend to 1/21/11.
1/27/11 Approved extension to 1/26/12; not built yet.
1/26/12 Approved extension to 1/24/13
1/24/13 Approved extension to 1/23/14;
1/23/14 Approved extension to 1/22/15; not built yet.
Recommendation: Extend to January 28, 2016. Construction has not begun on the third building yet.
Perf agreement: Stormwater drainage/detention $41,000
Established: January 26, 2006
Previous Action: 9/22/05 FMPC approval extended to 4/18/06.
3/30/06 PA posted
1/12/07 Approved extension to 1/24/08
1/24/08 Approved extension to 7/24/08
7/24/08 Approved extension to 7/23/09
7/23/09 Approved extension to 7/22/10
7/22/10 Reduce from $82,000; extend to 7/28/11
7/28/11 Approved extension to 1/26/12
1/26/12 Approved extension to 7/26/12
7/26/12 Extend to 1/24/13
1/24/13 Approved extension to 1/23/14
1/23/14 Approved extension to 1/22/15; site still under construction.
Recommendation: Extend to January 28, 2016. Construction has not begun on the third building yet.