AVALON PUD SUBDIVISION, SITE PLAN, SECTION 5
Perf agreement: Landscaping $60,000
Established: March 23, 2006
Previous Action: 2/13/08 PA posted
1/16/09 Approved extension to 1/15/10
1/15/10 Approved extension to 1/21/11; still under construction.
1/20/11 Approved extension to 1/20/12
1/20/12 Approved extension to 1/24/13
1/24/13 Approved extension to 1/23/14
1/23/14 Approved extension to 1/22/15; still under construction
Recommendation: Extend to January 28, 2016.
Reason/Deficiency: This section is still under construction and the required plant material is not installed.