FRANKLIN PARK PUD SUBDIVISION, SITE PLAN, (APARTMENTS)
Perf agreement: Landscaping $281,000
Established: May 23, 2013
Previous Action: 6/24/13 PA posted
6/20/14 Approved extension to 6/19/15
6/19/15 Approved extension to 6/17/16
6/17/16 Extend to 6/16/17; still under construction
Recommendation: Approved extension to June 28, 2018.
Perf agreement: Access $3,500
Established: May 23, 2013
Previous Action: 6/24/13 PA posted
6/20/14 Approved extension to 6/19/15
6/19/15 Approved extension to 6/17/16
6/17/16 Extend to 6/16/17; still under construction
Recommendation: Approved extension to December 14, 2017.
Perf agreement: Sidewalks $10,000
Established: May 23, 2013
Previous Action: 6/24/13 PA posted
6/20/14 Approved extension to 6/19/15
6/19/15 Approved extension to 6/17/16
6/17/16 Extend to 6/16/17; still under construction
Recommendation: Approved extension to December 14, 2017.
Perf agreement: Drainage $649,000
Established: May 23, 2013
Previous Action: 6/24/13 PA posted
6/20/14 Approved extension to 6/19/15
6/19/15 Approved extension to 6/17/16
6/17/16 Extend to 6/16/17; still under construction
Recommendation: Approved extension to December 14, 2017.