File #: 15-0579    Version: 1 Name:
Type: Report Status: Passed
File created: 6/15/2015 In control: Capital Investment Committee
On agenda: 6/25/2015 Final action: 6/25/2015
Title: Water and Sewer Projects Status Report
Sponsors: Engineering

DATE: June 25, 2015

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Mark Hilty, Director of Water Management
Paul Holzen, Director of Engineering

SUBJECT:
title
Water and Sewer Projects Status Report

body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's water and sewer projects.

Project Status
A. Spencer Creek Basin - South Prong Interceptor Upgrade
Key Dates: Design Start - April 23, 2013; Design Completion - June 2015*; Bid Date: Not Funded; Construction Start - Not Funded; Construction Completion - Not Funded
*Denotes Estimated Date
Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded
Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD
Status Update: Design plans are currently underway, but the project will not be constructed until funding is available from the Water Management Department budget.

B. Charlton Green Sanitary Sewer Improvements
Key Dates: Design Start - November 12, 2013; Design Completion - March 2014; Bid Date: April 7, 2014; Construction Start - December 1, 2014; Construction Completion - April 2015
Cost: Design - $19,895.00; Easement - $3,500.00; Construction -$465,304.90
Funding Source: Design -Sewer Operating; Construction - Sewer Fund
Status Update: The final change order is on the June 2015 CIC meeting agenda.

C. Spencer Creek at Franklin Road Sewer
Key Dates: Design Start - March 11, 2014; Design Completion - June 2015*; Easement Acquisition Start - June 2015*; Easement Acquisition Completion - August 2015*; Bid Date: September 2015*; Construction Start - November 2015*; Construction Completion - April 2016*
*Denotes Estimated Date
Cost: Design - $40,000.00; Easement - TBD; Construction - TBD
Funding Source: Design - Sewer Fund
Status Update: The SWPPP has bee...