Title: Cool Springs Life Science Center Subdivision, site plan; extend the performance agreement for stormwater drainage/detention improvements for ten months. (CONSENT AGENDA)

COOL SPRINGS LIFE SCIENCE CENTER SUBDIVISION, SITE PLAN

Perf agreement:                     Stormwater drainage/detention $27,000

Established:                     August 15, 2002

Previous Action:                     7/2/04 PA posted

7/15/04 FMPC approval extended to 12/15/04

10/14/05 Approved extension to 7/27/06

7/27/06 Approved extension to 1/25/07

1/25/07 Approved extension to 1/24/08

1/24/08 Approved extension to 1/22/09

1/22/09 Approved extension to 1/28/10

1/28/10 Approved extension to 1/27/11

1/27/11 Extend to 1/26/12

1/26/12 Approved extension to 1/24/13

1/24/13 Approved extension to 1/23/14

1/23/14 Approved extension to 1/22/15

1/22/15 Extend to 1/28/16; third building not started yet.

Recommendation:                     Extend to January 26, 2017.  Construction has not started on the third building.