File #: 15-0762    Version: 1 Name: RES 2015-71 Unspent funds allocation to Stormwater Div
Type: Resolution Status: Passed
File created: 8/13/2015 In control: Board of Mayor & Aldermen
On agenda: 9/8/2015 Final action: 9/8/2015
Title: Consideration of Resolution 2015-71, A Resolution Reallocating $20,925.00 in Unspent Funds from the Intersection of State Route 252 (Wilson Pike) and McEwen Drive Construction Project (COF Contract No. 2012-0145) to the Streets Department Stormwater Division FY2016 Annual Operations Budget (08/27/15 CIC 3-0)
Sponsors: Engineering
Attachments: 1. Estimate_Restoration.pdf, 2. Estimate_Hydroseeder.pdf, 3. Res 2015-71 Reallocating Funds from COF 2012-0145.pdf

 

DATE:                                                               August 27, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          David Parker, City Engineer/CIP Executive

                                          Joe York, Director of Streets

                                          Paul Holzen, Director of Engineering

                                          Jonathan Marston, Staff Engineer 3                     

                                          

SUBJECT:                                          

title

Consideration of  Resolution 2015-71, A Resolution Reallocating $20,925.00 in Unspent Funds from the Intersection of State Route 252 (Wilson Pike) and McEwen Drive Construction Project (COF Contract No. 2012-0145) to the Streets Department Stormwater Division FY2016 Annual Operations Budget (08/27/15 CIC 3-0)

body

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Resolution 2015-71 to reallocate $20,925.00 in unspent funds from the Intersection of State Route 252 (Wilson Pike) and McEwen Drive construction project (COF Contract No. 2012-0145) to the Streets Department Stormwater Division FY2016 annual operations budget.

 

Background

As a part of the intersections improvements project (COF Contract No. 2012-0145) the City’s contractor constructed a left-turn lane on Wilson Pike.  This widening of Wilson Pike required grading and ditch work in front of several residences along Wilson Pike.  Unfortunately, the construction ended during late November 2014, when it was difficult to restore the area to its original condition.  Therefore, the contractor focused on simply stabilizing the area, which allowed the City to terminate its permit for this work with the state.  The City assured the affect property owners that it or a landscaping contractor would return to restore the affected properties to their original state.  After tabulation of final cost overruns and underruns for the intersection project, $200,469.88 in original contract funds remain unspent.

 

After a recent site visit by City Staff from both the Engineering and Streets Departments, it was determined that this minor ditch and landscape restoration work could be performed by Streets Department crews.  The Streets Department estimated a total cost of approximately $6,000.00 to perform this work.  This cost does not include the purchase or rental of a hydroseeding unit.

 

The Streets Department has programmed $16,000.00 in their Stormwater Division FY2016 annual operations budget for the purchase of a small, truck mounted hydroseeding unit to efficiently spread seed and fertilizers.  This equipment could be utilized to perform the seeding and fertilizing along the Wilson Pike properties.  With additional funding of $14,925.00, the Streets Department could purchase a larger, trailer mounted hydroseeding unit, which is more capable and efficient than the smaller, truck mounted design.  The total cost of this larger unit is $30,925.00.

 

Staff sees this opportunity as a winning solution for all parties:

                     City staff can perform this minor restoration work much faster than hiring a third party landscaping company,

                     Properties along Wilson Pike that were disturbed as a part of the intersection improvements project will be restored to their original condition by City staff, who can return, if needed, to get the work done right, and

                     The Streets Department would be able to purchase a larger, more capable hydroseeding unit that can and will be utilized for future landscaping projects.

 

Financial Impact

The total cost for the larger hydroseeding unit is $30,925.00.  The total cost of the labor and materials needed to perform the restoration work is approximately $6,000.00.  The Streets Department has programmed $16,000.00 in its Stormwater Division FY2016 annual operations budget (83530 - Machinery & Equipment <$25k) for the purchase of a hydroseeding unit.  The remaining $20,925.00 can be reallocated from the unspent capital project funds for the intersection improvements project (COF Contract No. 2012-0145)

 

Recommendation

rec

Staff recommends approval of Resolution 2015-71 to reallocate $20,925.00 in unspent funds from the Intersection of State Route 252 (Wilson Pike) and McEwen Drive construction project (COF Contract No. 2012-0145) to the Streets Department Stormwater Division FY2016 annual operations budget.