File #: 15-0578    Version: 1 Name:
Type: Report Status: Passed
File created: 6/15/2015 In control: Capital Investment Committee
On agenda: 6/25/2015 Final action: 6/25/2015
Title: Transportation Projects Status Report
Sponsors: Engineering
 
DATE:                  June 25, 2015
 
TO:            Board of Mayor and Aldermen
 
FROM:            Eric Stuckey, City Administrator
            David Parker, City Engineer/CIP Executive
            Paul Holzen, Director of Engineering      
            
SUBJECT:            
title
Transportation Projects Status Report
body
 
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's transportation projects.
 
Project Status
A.      Mack Hatcher Parkway NW Extension
BOMA Priority Ranking: N/A (Highest Priority)
Key Dates: Design Start - August 14, 2007 (BOMA Approval); Re-Design Completion - January 2015; ROW Start - December 2009; ROW Completion - June 2012; Construction Start - Currently Not Funded; Construction Completion - Currently Not Funded
Cost: Design - $3,502,501; ROW - $13,397,520 (Provided by TDOT); Construction - $58,700,000 (Provided by TDOT)
Status Update:  TDOT has agreed to build the full intersections at SR96, Hillsboro Road and Del Rio Pike as a part of the 2-lane Mack Hatcher Parkway construction.  On Thursday, April 9TH, the City received notification from the TDOT Communications Office of projects on the Statewide Transportation Improvement Plan (STIP) for the 3-year period from 2016-2018, and this project was not included.  A field review of the construction plans was held at TDOT's Region 3 offices in Nashville, TN on April 16TH.  The designer is completing final plans comments, as requested by TDOT.
 
B.      Hillsboro Road Improvements Phase 2 (Independence Square to Mack Hatcher Pkwy)
BOMA Priority Ranking: #1
Key Dates: Design Start - March 24, 2008 (BOMA Approval); Design Completion - March 2015; ROW Start - March 2013; ROW Completion - May 2015; Bid Date - Late July 2015*; Construction Start - September 2015*; Construction Completion - December 2016*
*Denotes Estimated Date
Cost: Design - $1,324,221 (Design fees include the SR96-IndSq Project as well); ROW - $3,000,000; Construction - $13,217,983.82 ($1,750,000 Reimbursable through State and Federal Approved Funding; Includes AT&T and ATMOS Reimbursable items totaling $590,470.60)
Status Update:  ROW Acquisition was certified by TDOT.  Condemnation proceedings have started for certain parcels.  Construction Plans are complete and submitted to TDOT for review and approval.  Will hopefully have TDOT concurrence to bid the project in late June.    
 
C.      Carothers Parkway South Extension
BOMA Priority Ranking: #5
Key Dates: Design Start - July 10, 2007; Design Completion - March 2013*; ROW Start - May 26, 2009; ROW Completion - March 2011; Bid Date - April 2013; Construction Start - September 1, 2013; Construction Completion - September 2015* (Substantial Completion)
*Denotes Estimated Date
Cost: Design - $2,116,560; ROW - $500,000.00 (Estimated); CEI Services - $1,113,500 (Approved Contract); Construction - $13,292,567.42 (Approved Contract and COs)
Status Update:  Bridge crews continue to work on the bridge.  Crews have begun pouring roadway lighting foundations and setting light poles.  Work continues on the sidewalk, along the north side of the Harpeth River.  Work also continue on the water line and gas line across the Harpeth River bridge.
 
D.      McEwen Drive at Wilson Pike Intersection Improvements Project
Key Dates: Design Start - October 2010; Design Completion - September 2012; ROW Start - October 2011; ROW Completion - September 2013; Bid Date - October 2012; Construction Start - July 8, 2013; Construction Completion - December 2014
BOMA Priority Ranking: N/A
Cost: Design - $206,363; ROW - $395,500 (Estimate); CEI Services - $207,000 Construction - $1,991,572.82 (bid amount)
Status Update:  Punch list items are complete.  The final change order for this project will appear on an upcoming agenda.  Because this project was finished during the winter months, a landscaping contractor will need to return to complete the restoration of yards.
 
E.      Century Court / Beasley Drive Connector
Key Dates: Design Start - May 8, 2007; Design Complete - March 2015*; ROW Start - March 2008; ROW Complete -March 2015*; Bid Date - June 2015; Construction Start - August 2015*; Construction Complete - December 2015*
*Denotes Estimated Date
Cost: Design - $27,526; ROW - $153,450; Construction - TBD
Status Update:  Utilities have begun relocations.  This project is currently out to bid, with the bid opening scheduled for July 8TH.
      
F.      Hunter's Bend Safe Routes to School
Key Dates: Design Start- January 2014; Design Complete - May 2014*; ROW Start - N/A; ROW Complete - N/A; Bid Date - July 2015* Construction Start - August 2015*; Construction Complete - October 2015*
*Denotes Estimated Date
Cost: Total - $289,565 (Estimated)
Status Update:  Design plans have been submitted by TDOT.  Bidding for construction cannot occur without a Notice to Proceed from TDOT; the City is awaiting this notice.  As soon as this Notice to Proceed is issued by TDOT, we can proceed with bidding and construction.
 
G.      Multiuse Trail along Highway 96 West, Vintage Grove Lane to Freedom Middle School
Key Dates: Design Start- June 2014; Design Complete - September 2014*; ROW Start - March 2015*; ROW Complete - June 2015*; Bid Date - July 2015*; Construction Start - August 2015*; Construction Complete - November 2015*
*Denotes Estimated Date
Cost: Construction - $675,000 (Estimated)
Status Update:  Final design of this project is complete and was performed in-house by Paul Holzen, the Engineering Director.  Negotiations for easement acquisitions have begun.  This project, along with several others, is currently out for bids, with a bid opening date of July 8TH.
 
H.      Sidewalk along Murfreesboro Road (SR 96 East), Pinkerton Park to Mack Hatcher Parkway
Key Dates: Design Start- June 2014; Design Complete*; ROW Start - TBD*; ROW Complete - TBD*; Bid Date - TBD*; Construction Start - TBD*; Construction Complete - TDBD*
*Denotes Estimated Date
Cost: Total - TBD upon final design decision by the BOMA
Status Update:  TDOT has given a verbal approval on the current design.  A second public meeting was held on March 4, 2015, and a discussion about the results of that public meeting was held at the April 23RD CIC meeting.  The main takeaway from the latest public meeting was a general request to provide a multi-use trail, rather than a sidewalk, along SR-96.  Further discussion of this project will occur at the May 12TH BOMA Work Session.
 
I.      Franklin Road (Harpeth River Bridge to Harpeth Industrial Court)
Key Dates: Design Start- January 2015; Design Complete - January 2016*;
ROW Acquisition- Not Funded; Construction - Not Funded
*Denotes Estimated Date
Cost: Total - $10,344,250 (Estimated)
Status Update:  Final Design PSA was approved by BOMA on October 14, 2014.  The survey update is complete.  Design updates are ongoing.
 
J.      3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase 1)
Key Dates: Design Start - April 11, 2006; Design Completion - February 2013; ROW Start - October 9, 2007; ROW Completion - January 26, 2010; Bid Dates - July 2015; Construction Start - September 2015*; Construction Completion - July 2016*
*Denotes Estimated Date
Cost: Design $65,725.00 (This number does not include design cost from the Bicentennial Park Project); ROW $226,500.00; Construction Bid Estimate $1,444,000.00
Status Update: The project has been bid twice now.  TDOT would not concur with the second bid because of subcontractor issues.  Project is currently out to bid for the third time.  Bid opening on July 8, 2015.
 
K.      East McEwen Drive Phase 4 Improvements
Key Dates: Design Start - April 2015; Design Completion - April 2016*; ROW Acquisition - Not Funded; Construction - Not Funded
*Denotes Estimated Date
Cost: Design - $1,210,000 (Preliminary - $497,000; Final - $713,000); ROW - Not Funded; Construction - Not Funded
Status Update:  The PSA for final design (COF Contract No. 2015-0052) was approved by the BOMA at their March 24TH meeting.  Updates to the original survey have begun.
 
L.      Columbia Avenue (Mack Hatcher Parkway to Downs Boulevard)
Key Dates & Cost: TBD upon final approval of Local Agency Project Agreement between TDOT and the City of Franklin
Cost: TBD (current total estimate is $21M)
Status Update:  The Local Agency Project Agreement, which allows the City to manage the Columbia Avenue project, while still receiving federal and state funding, has been finalized.  It will go to the Board for approval in the next month or so.   The City has received permission from TDOT to proceed with the selection of a design consultant for the project.  As soon as this agreement is finalized and signed, the City can move forward with Preliminary Engineering and Environmental.