File #: 15-0988    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 10/16/2015 In control: Board of Mayor & Aldermen
On agenda: 11/10/2015 Final action: 11/10/2015
Title: Consideration of Change Order No. 1 to the Construction Contract (COF Contract No. 2014-0301) with J.S. Haren for the Fieldstone Farms Pump Station No. 1 Rehabilitation Project for a cost INCREASE of $109,522.00 (10/29/15 CIC 4-0)
Sponsors: Engineering
Attachments: 1. Change Order No 1.pdf, 2. Change Order No 1 email from contractor.pdf

 

DATE:                                                               October 29, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          David Parker, City Engineer/CIP Executive

                                          Mark Hilty, Director of Water Management

                                          Paul Holzen, Director of Engineering

                                          Patricia Proctor, Utilities Project Manager

                                          

SUBJECT:                                          

title

Consideration of Change Order No. 1 to the Construction Contract (COF Contract No. 2014-0301) with J.S. Haren for the Fieldstone Farms Pump Station No. 1 Rehabilitation Project for a cost INCREASE of $109,522.00 (10/29/15 CIC 4-0) 

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Change Order No. 1 to COF Contract No. 2014-0301 with J.S. Haren to raise the wetwell walls, valve vault walls, and the electric room slab and to include a contingency line item with the project.

 

Background

The project was submitted to the Building and Neighborhood Services Department for review and approval during the bidding phase.  It was determined during that review that the wetwell walls, valve vault walls, and the electric room slab needed to be raised in order to be one (1) vertical foot above the existing floodplain elevation.  The contractor has submitted a cost of $9,522.00 to perform this additional work.  This estimate is acceptable for the amount of work to be done.

 

After the project was bid, the consultant and City Staff discussed the practicality of including a contingency line item to the project.  This would allow the project to keep moving in the case of unforeseen circumstances.  This change order includes a request of $100,000.00 to establish a project contingency.

 

Financial Impact

The cost as negotiated with J.S. Haren for the additional work and contingency line item is a total amount not to exceed $109,522.00 ($9,522.00 for the onsite work and $100,000.00 for the contingency line item number amount).  The original bid amount was $1,592,000.00, which is lower than the preliminary cost estimate of $2,756,000.00 for construction of a new pump station.  The proposed change order amount of $109,522.00 is anticipated to come from the same fund that the pump station construction is currently being paid out of, which is the Sewer Operating Fund.

 

Recommendation

rec

Staff recommends approval of Change Order No. 1 to the construction contract (COF Contract No. 2014-0301) with J.S. Haren for the Fieldstone Farms Pump Station No. 1 Rehabilitation Project at a cost INCREASE not to exceed $109,522.00.