File #: 16-0289    Version: 1 Name:
Type: Report Status: Passed
File created: 3/16/2016 In control: Capital Investment Committee
On agenda: 3/24/2016 Final action: 3/24/2016
Title: Transportation Projects Status Report
Sponsors: Engineering

 

DATE:                                                               March 24, 2016

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, Director of Engineering                     

                                          

SUBJECT:                                          

title

Transportation Projects Status Report

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning status of some of the City’s transportation projects.

 

Project Status

 

A.                     Mack Hatcher Parkway NW Extension

Key Dates: Design Start - August 14, 2007 (BOMA Approval); Re-Design Completion - January 2015; ROW Start - December 2009; ROW Completion - June 2012; Construction - Not Funded

Cost: Design - $3,502,501; ROW - $13,397,520 (Provided by TDOT); Construction - $58,700,000 (Provided by TDOT)

Status Update:  TDOT has agreed to build the full intersections at SR96, Hillsboro Road and Del Rio Pike as a part of the 2-lane Mack Hatcher Parkway construction.  On February 17, 2016, the Nashville Area Metropolitan Planning Organization (MPO) Executive Board approved the 2040 Regional Transportation Plan (RTP).  Being listed in this plan is the first step for transportation projects to receive federal funding.  The Mack Hatcher Parkway NW Extension is listed as one of the short term projects for funding.  Ultimately though, the decision to proceed with construction lies with TDOT.

 

B.                     Hillsboro Road Improvements Phase 2 (Independence Square to Mack Hatcher Pkwy)

Key Dates: Design Start - March 24, 2008 (BOMA Approval); Design Completion - March 2015; ROW Start - March 2013; ROW Completion - May 2015; Bid Date - January 2016; Construction Start - May 2016*; Construction Completion - August 2017*

*Denotes Estimated Date

Cost: Design - $1,324,221 (Design fees include the SR96-IndSq Project as well); ROW - $3,000,000; Construction - $11,995,005.13 ($1,750,000 Reimbursable through State and Federally Approved Funding; Includes AT&T and ATMOS Reimbursable items totaling $441,677.00)

Status Update:  Bid opening was held on January 22, 2016.  TDOT would not concur with the low bid, and deemed it non-responsive.  TDOT concurred with the 2nd lowest bidder, Eutaw Construction Company. BOMA approved the construction contract with Eutaw on March 8, 2016.  A preconstruction meeting is tentatively scheduled for April 5th.   Construction could start in May.  Also, a neighborhood meeting will be held with the affected property owners before construction starts. 

 

C.                     Carothers Parkway South Extension

Key Dates: Design Start - July 10, 2007; Design Completion - March 2013; ROW Start - May 26, 2009; ROW Completion - March 2011; Bid Date - April 2013; Construction Start - September 1, 2013; Construction Completion - September 23, 2015 (Substantial Completion)

Cost: Design - $2,116,560; ROW - $500,000.00 (Estimated); CEI Services - $1,113,500 (Approved Contract); Construction - $13,292,567.42 (Approved Contract and COs)

Status Update:  Project was opened to traffic on September 23, 2015.  There are a few pavement related items that will not be addressed until April.

 

D.                     Century Court / Beasley Drive Connector

Key Dates: Design Start - May 8, 2007; Design Complete - March 2015*; ROW Start - March 2008; ROW Complete -March 2015; Bid Date - June 2015; Construction Start - November 2015; Construction Complete - July 2016*

*Denotes Estimated Date

Cost: Design - $27,526; ROW - $153,450; Construction - $399,250.97 (Bid Amount)

Status Update:  Contractor has built about 30 percent of the roadway. AT&T has still not completed relocation and wet weather has made progress difficult. Contractor to place curbing and asphalt near Beasley drive within the next month.

                     

E.                     Hunter’s Bend Safe Routes to School

Key Dates: Design Start- January 2014; Design Complete - December 2015; ROW Acquisition - N/A; Construction - Summer 2016*

*Denotes Estimated Date

Cost: Total - $289,565 (Estimated)

Status Update:  The designer has resubmitted final plans with requested corrections to TDOT for final approval.  Bidding for construction cannot occur without a Notice to Proceed from TDOT; the City is awaiting this notice.  As soon as this Notice to Proceed is issued by TDOT, we can proceed with bidding and construction.

 

F.                     Multiuse Trail along Highway 96 West, Vintage Grove Lane to Freedom Middle School

Key Dates: Design Start- June 2014; Design Complete - September 2014; ROW Start - March 2015; ROW Complete - July 2015; Bid Date - July 2015; Construction Start - February 2016; Construction Complete - June 2016*

*Denotes Estimated Date

Cost: Construction - $596,116.10 (Bid Amount)

Status Update:  Contractor has completed installation of erosion prevention and sediment control devices.

 

G.                     Sidewalk/Multi-use Trail along Murfreesboro Road (SR 96 East), Pinkerton Park to Mack Hatcher Parkway

Key Dates: Design Start- June 2014; Design Complete - TBD;

ROW Acquisition - TBD; Construction - TBD

*Denotes Estimated Date

Cost: Total - $2,148,000 (Estimated)

Status Update:  As directed by the BOMA, City Staff has completed the design plans to show a multi-use trail as directed by the BOMA.  After a public meeting on January 27, 2016, this project was discussed by the BOMA at their February 9TH and March 8TH work sessions.  BOMA was generally in favor of proceeding with a 5-foot sidewalk.  A resolution to proceed with the project will be presented to the BOMA in April.

 

H.                     Franklin Road (Harpeth River Bridge to Harpeth Industrial Court)

Key Dates: Design Start- January 2015; Design Complete - June 2016*;

ROW Acquisition- Not Funded; Construction - Not Funded

*Denotes Estimated Date

Cost: Total - $10,344,250.00 (Estimated)

Status Update:  Water and Sanitary Sewer design contracts were approved by BOMA on October 13, 2015.   Design updates are still ongoing.

 

I.                     3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase 1)

Key Dates: Design Start - April 11, 2006; Design Completion - February 2013; ROW Start - October 9, 2007; ROW Completion - January 26, 2010; Bid Dates - July 8, 2015; Construction Start - September 21, 2015; Construction Completion - May 17, 2016 (240 Calendar Day Contract)

*Denotes Estimated Date

Cost: Design - $65,725.00 (This number does not include design cost from the Bicentennial Park Project); ROW - $226,500.00; Construction - $1,253,257.31 (Bid Amount)

Status Update:  The bid was awarded to Jones Bros Contractors, LLC on August 11, 2015.  Contractor’s notice to proceed was issued for September 21st.  Contractor currently has until May 17th to complete the project.  There have been many weather impact days because of rain, which will require a time extension.  Engineering Staff will bring forward a time extension to the Board in the next few months.  Construction is ongoing.

 

J.                     East McEwen Drive Phase 4 Improvements

Key Dates: Design Start - April 2015; Design Completion - November 2016*;

ROW Acquisition - Not Funded; Construction - Not Funded

*Denotes Estimated Date

Cost: Design - $1,210,000 (Preliminary - $497,000; Final - $713,000);

ROW Acquisition - Not Funded; Construction - Not Funded

Status Update:  Designer continues work on the Final Design plans.

 

K.                     Columbia Avenue (Mack Hatcher Parkway to Downs Boulevard)

Key Dates: Preliminary Design/Environmental Start - March 2016; Preliminary Design/Environmental Completion - August 2017;

Final Design- TBD; ROW Acquisition- TBD; Construction - TBD

*Denotes Estimated Date

Cost: Preliminary Design/Environmental - $1,070,450.00; Final Design - $1,000,000.00*; ROW - $4,000,000.00*; Construction - $15,000,000.00*. Currently funded by 80% Federal/20% State/0% Local. Total project estimate is $21MM. 

*Denotes Estimated Cost per MPO TIP, FY2014-2017

 

Status Update:  The PSA and Scope of Services for preliminary design (environmental) phase were approved by BOMA on February 9, 2016, and work began in March.  A kick-off meeting took place on February 22nd.  A public involvement plan will be taken to the Board in April for review and discussion.