GENERALS RETREAT PUD SUBDIVISION, SITE PLAN
Perf agreement: Sidewalk $6,000
Established: February 23, 2006
Previous Action: 6/27/06 PA posted
4/13/07 Approved extension to 4/24/08
4/24/08 Approved extension to 4/23/09
4/17/09 Approved extension to 4/16/10
4/22/10 Extend to 4/28/11
4/28/11 Approved extension to 4/26/12
4/26/12 Extend to 4/25/13
4/25/13 Extend to 10/24/13
10/24/13 Approved extension to 3/27/14
12/23/13 NEW APPLICANT
3/27/14 Approved extension to 3/26/15
3/26/15 Approved extension to 3/24/16
3/24/16 Extend to 3/23/17
Recommendation: Accept the sidewalk improvements, release the performance agreement and establish a maintenance agreement in the amount of $2,500 for one year.
Perf agreement: Streets $98,000
Established: February 23, 2006
Previous Action: 6/27/06 PA posted
4/13/07 Approved extension to 4/24/08
4/24/08 Approved extension to 4/23/09
4/17/09 Approved extension to 4/16/10
4/22/10 Extend to 4/28/11
4/28/11 Approved extension to 4/26/12
4/26/12 Extend to 4/25/13
4/25/13 Extend to 10/24/13
10/24/13 Approved extension to 3/27/14
12/23/13 NEW APPLICANT
3/27/14 Approved extension to 3/26/15
3/26/15 Approved extension to 3/24/16
3/24/16 Extend to 3/23/17
Recommendation: Accept the streets improvements, release the performance agreement and establish a maintenance agreement in the amount of $9,800 for one year.
Perf agreement: Drainage/detention $5,000
Established: February 23, 2006
Previous Action: 6/27/06 PA posted
4/13/07 Approved extension to 4/24/08
8/23/07 Reduce from $10,000; extend to 8/28/08
8/15/08 Approved extension to 2/20/09
2/20/09 Release denied; extend to 2/19/10
2/19/10 Extend to 2/18/11
2/24/11 Extend to 2/23/12
2/23/12 Approved extension to 2/28/13
2/28/13 Extend to 2/27/14; portion of site still under construction
12/23/13 NEW APPLICANT
2/27/14 Extend to 2/26/15; part of site still under construction
2/26/15 Extend to 2/25/16
2/25/16 Extend to 2/23/17
Recommendation: Extend to November 17, 2016.
Reason/Deficiency: The applicant shall address the punchlist items, as discussed with the stormwater inspector. Drainage as-builts shall be submitted, as required.