File #: 15-0241    Version: 1 Name:
Type: Report Status: Agenda Ready
File created: 2/24/2015 In control: Capital Investment Committee
On agenda: 3/4/2015 Final action:
Title: Street Projects Status
Sponsors: Engineering
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
 
DATE:                  March 4, 2015
 
TO:            Board of Mayor and Aldermen
 
FROM:            Eric Stuckey, City Administrator
            David Parker, City Engineer/CIP Executive
            Paul Holzen, Director of Engineering
      
            
SUBJECT:            
title
Street Projects Status
body
 
Purpose
The purpose of this memo is to update the City of Franklin Board of Mayor and Aldermen (BOMA) with the current status of some of the City's street projects.
 
Project Status
 
A.      Mack Hatcher Parkway NW Extension
BOMA Priority Ranking: N/A (Highest Priority)
Key Dates: Design Start - August 14, 2007 (BOMA Approval); Re-Design Completion - January 2015; ROW Start - December 2009 (ROW Meeting Scheduled); ROW Completion - June 2012; Construction Start - Currently Not Funded; Construction Completion - Currently Not Funded
Cost: Design - $3,502,501; ROW - $13,397,520 (Provided by TDOT); Construction - $58,700,000 (Provided by TDOT)
Status Update:  TDOT has agreed to build the full intersections at SR96, Hillsboro Road and Del Rio Pike as a part of the 2-lane Mack Hatcher Parkway construction.  The designer is completing final plans comments, as requested by TDOT.
 
B.      Hillsboro Road Improvements Phase 2 (Independence Square to Mack Hatcher Pkwy)
BOMA Priority Ranking: #1
Key Dates: Design Start - March 24, 2008 (BOMA Approval); Design Completion - February 2015; ROW Start - March 2013; ROW Completion - March 2015*; Bid Date - May 2015*; Construction Start - July 2015*; Construction Completion -September 2016*
*Denotes Estimated Date
Cost: Design - $1,324,221 (Design fees include the SR96-IndSq Project as well); ROW - $3,000,000; Construction - $12,500,000.00 ($1,750,000 Reimbursable through State and Federal Approved Funding)
Status Update:  ROW Acquisition is still ongoing.  All offers have been made.  Waiting on closings and condemnation proceedings to start.  Construction Plans are complete.  Will hopefully have TDOT concurrence to bid the project in March/April.    
 
C.      Carothers Parkway South Extension
BOMA Priority Ranking: #5
Key Dates: Design Start - July 10, 2007; Design Completion - March 2013*; ROW Start - May 26, 2009; ROW Completion - March 2011; Bid Date - April 2013*; Construction Start - September 1, 2013; Construction Completion - September 2015* (Substantial Completion)
*Denotes Estimated Date
Cost: Design - $2,116,560; ROW - $500,000.00 (Estimated); CEI Services - $1,113,500 (Approved Contract); Construction - $13,292,567.42 (Approved Contract and COs)
Status Update: The contractor continues work on the installation of fiber optic conduit and electrical conduit for street lights.  As weather allows, bridge crews are expected to return to begin work on the bridge deck.
 
D.      McEwen Drive at Wilson Pike Intersection Improvements Project
Key Dates: Design Start - October 2010; Design Completion - September 2012; ROW Start - October 2011; ROW Completion - September 2013; Bid Date - October 2012; Construction Start - July 8, 2013; Construction Completion - December 2014
BOMA Priority Ranking: N/A
Cost: Design - $206,363; ROW - $395,500 (Estimate); CEI Services - $207,000 Construction - $1,991,572.82 (bid amount)
Status Update:  Punch list items are complete.  The final change order for this project will appear on an upcoming agenda.  Because this project was finished during the winter months, a landscaping contractor will need to return in the Spring to complete the restoration of yards.
 
E.      Century Court / Beasley Drive Connector
Key Dates: Design Start - May 8, 2007; Design Complete - March 2015*; ROW Start - March 2008; ROW Complete -March 2015*; Bid Date - May 2015*; Construction Start - July 2015*; Construction Complete - November 2015*
*Denotes Estimated Date
Cost: Design - $27,526; ROW - $153,450; Construction - TBD
Status Update:  Middle Tennessee Electric and AT&T to start relocation this month.
      
F.      Hunter's Bend Safe Routes to School
Key Dates: Design Start- January 2014; Design Complete - May 2014*; ROW Start - N/A; ROW Complete - N/A; Bid Date - April 2015* Construction Start - May 2015*; Construction Complete - August 2015*
*Denotes Estimated Date
Cost: Total - $289,565 (Estimated)
Status Update:  Design plans have been approved by TDOT.  Bidding for construction cannot occur without a Notice to Proceed from TDOT; the City is awaiting this notice.  Construction is expected to begin in late spring.  A time extension from TDOT for completion of this project will appear on an upcoming agenda.
 
G.      Multiuse Trail along Highway 96 West, Vintage Grove Lane to Freedom Middle School
Key Dates: Design Start- June 2014; Design Complete - September 2014*; ROW Start - March 2015*; ROW Complete - May 2015*; Bid Date - May 2015*; Construction Start - July 2015*; Construction Complete - October 2015*
*Denotes Estimated Date
Cost: Construction - $675,000 (Estimated)
Status Update:  Final design of this project is complete and was performed in-house engineering staff.  Easement acquisition will begin this month, acquiring all necessary permits.
 
H.      Sidewalk along Murfreesboro Road (SR 96 East), Pinkerton Park to Mack Hatcher Parkway
Key Dates: Design Start- June 2014; Design Complete - April 2015*; ROW Start - April 2015*; ROW Complete - July 2015*; Bid Date - July 2015*; Construction Start - September 2015*; Construction Complete - December 2015*
*Denotes Estimated Date
Cost: Total - $550,300 (Estimated)
Status Update:  Design on this project is well underway.  TDOT has given a verbal approval on the current design.  A public meeting was held on February 19, 2015 and another public meeting is scheduled for March 5, 2015 at 5p.m.
 
I.      Franklin Road (Harpeth River Bridge to Harpeth Industrial Court)
Key Dates: Design Start- January 2015; Design Complete - December 2015*;
ROW Acquisition- Not Funded; Construction - Not Funded
*Denotes Estimated Date
Cost: Total - $10,344,250 (Estimated)
Status Update:  Final Design PSA was approved by BOMA on October 14, 2014.  The survey update started in February.  
 
J.      3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase 1)
Key Dates: Design Start - April 11, 2006; Design Completion - February 2013; ROW Start - October 9, 2007; ROW Completion - January 26, 2010; Bid Dates - September 10, 2014 and December 18, 2014; Construction Start - June 2015*; Construction Completion - May 2016*
*Denotes Estimated Date
Cost: Design $65,725.00 (This number does not include design cost from the Bicentennial Park Project); ROW $226,500.00; Construction Bid Estimate $1,444,000.00
Status Update: The project has been bid twice now.  TDOT will not concur with the second bid.  Project will be re-bid again in April or May.
 
K.      East McEwen Drive Phase 4 Improvements
Key Dates: Design Start - April 2015*; Design Completion - December 2016*; ROW Acquisition - Not Funded; Construction - Not Funded
*Denotes Estimated Date
Cost: Design - $1,210,000 (Preliminary - $497,000; Final Design - $713,000); ROW - Not Funded; Construction - Not Funded
Status Update:  The PSA for final design of this project is on the March 2015 CIC agenda for a recommendation to the full BOMA.  If fully approved, design could begin as early as April 2015.