Title: Water and Sewer Projects Status Report

 

DATE:                                                               April 25, 2016

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, Director of Engineering

                     

                                          

SUBJECT:                                          

title

Water and Sewer Projects Status Report

body

 

Purpose

 

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City’s water and sewer projects.

 

Project Status

 

A.                     Spencer Creek Basin - South Prong Interceptor Upgrade

Key Dates: Design Start - April 23, 2013; Design Completion - June 2016*;

Easement Acquisition - TBD; Construction - Not Funded

*Denotes Estimated Date

Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded

Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD

Status Update:  Design plans are still being developed and are approximately 90% complete.  The project will not be constructed until funding is available from the Water Management Department budget.

 

B.                     Spencer Creek at Franklin Road Sewer

Key Dates: Design Start - March 11, 2014; Design Completion - June 2015; Easement Acquisition Start - September 2015; Easement Acquisition Completion - August 2016*; Bid Date: October 2016*; Construction Start - December 2016*; Construction Completion - September 2017*

                     *Denotes Estimated Date

Cost: Design - $40,000.00; Easement - TBD; Construction - TBD

Funding Source: Design - Sewer Fund

Status Update:  The plans are 100% complete.  Easement acquisition is still underway.

 

 

 

C.                     Curd Branch and Watson Branch Interceptor Sewer

Key Dates: Design Start - February 25, 2014; Design Completion - September 2015; Easement Acquisition Start - February 2015; Easement Acquisition Completion - May 2016*; Bid Date: July 2016*; Construction Start -September 2016*; Construction Completion - August 2017*

*Denotes Estimated Date

Cost: Design - $115,000.00; Easement - TBD; Construction - TBD

Funding Source: Design - Sewer Fund

Status Update:  Design plans are 100% complete but will not be submitted to TDEC for approval until the easements are obtained.  The remaining easements are in condemnation and at this time there is still not a court date. 

 

D.                     Fieldstone Farms Pump Station No. 1 Rehabilitation

Key Dates: Design Start - January 14, 2014; Design Completion - November 2014; Bid Date: December 11, 2014; Construction Start - July 2015; Construction Completion - September 2016

Cost: Design - $226,848.00; CEI - $196,000.00; Construction - $1,701,522.00

Funding Source: Design - Sewer Fund; Construction - Sewer Operating Fund

Status Update:  Work on the wetwell continues.  The concrete for the valve vault has been poured.

 

E.                     Goose Creek Sanitary Sewer Extension Project from West of I65 to the East Side of I65

Key Dates: Design Start - September 9, 2014; Design Completion - April 2015; Easement Acquisition Start - July 2015*; Easement Acquisition Completion - May 2016*; Bid Date: July 2016*; Construction Start - August 2016*; Construction Completion - June 2017*

*Denotes Estimated Date

Cost: Design - $132,535.00; Easements - TBD; Construction - TBD

Funding Source: Design, Easements, Construction - Sewer Fund & HPT TA Properties Trust

Status Update:  Design is complete.  All but one easement has been obtained.  The remaining easement is ready to file for condemnation.

 

F.                     Bobby Drive Water Line Improvement Project

Key Dates: Design Start - May 12, 2015; Design Completion - April 2016; Easement Acquisition Start - April 2016*; Easement Acquisition Completion - August 2016*; Construction - To be completed in-house by Water Management Department staff

*Denotes Estimated Date

Cost: Design - $80,313.00; Easements - TBD; Construction - TBD (Materials Only)

Funding Source: Design and Easements - Water Operating Fund

Status Update:  Design plans are 95% complete.  The ARAP permit has been applied for to cross any creeks on the project.

 

 

 

G.                     Old Carters Creek Water Line Improvements

Key Dates: Design Start - May 12, 2015; Design Completion - May 2016; Easement Acquisition Start - April 2016*; Easement Acquisition Completion - July 2016*; Construction - to be completed in-house by Water Management Department staff

*Denotes Estimated Date

Cost: Design - $79,498.00; Easements - TBD; Construction - TBD (Materials Only)

Funding Source: Design and Easements - Water Operating Fund

Status Update:  Design of the water line is still underway. 

 

H.                     James Street and Avondale Street Water and Sanitary Sewer Improvements Project

Key Dates: Design Start - May 12, 2015; Design Completion - November 2015; Construction - to be completed in-house by Water Management Department staff

*Denotes Estimated Date

Cost: Design - $83,350.00; Construction - TBD (Materials Only)

Funding Source: Design - Water and Sewer Operating Funds

Status Update:  Plans have been approved by TDEC.  No easements are necessary for this project.  The water line portion and a small section of the sanitary sewer line work will be done in -house with Water Management Department crews.  The lining portion of the project for the sanitary sewer will be done with the Annual Sewer Rehabilitation Contract.