File #: 15-1043    Version: 1 Name:
Type: Presentation Status: Agenda Ready
File created: 11/10/2015 In control: Work Session
On agenda: 11/24/2015 Final action:
Title: Project Status Update for the SR 96 East Sidewalk Project - Pinkerton Park to Mack Hatcher Parkway
Sponsors: Paul Holzen
Attachments: 1. 11-10-2015 PUBLIC MEETING EXHIBITS

 

DATE:                                                               November 10, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          David Parker, City Engineer

                                          Paul Holzen, Director of Engineering

                                                               

SUBJECT:                                          

title

Project Status Update for the SR 96 East Sidewalk Project - Pinkerton Park to Mack Hatcher Parkway

body

 

Purpose

The purpose of this memorandum is to provide the Board of Mayor and Aldermen (BOMA) with a status updated for the SR 96 East Sidewalk Project.

 

Background

As part of Resolution 2014-13, A Resolution to Adopt the Funding Plan for the FYI 2014-2018 CIP (Capital Investment Program) the Board approved $550,300 for a sidewalk project from Pinkerton Park to Mack Hatcher Parkway along HWY 96 E.  On 2/19/2015 and 3/4/2015 a public hearing was held to obtain feedback from the local residents and the general public.  The project was well supported by the residents with the majority of people in favor of the project.  At the May 26, 2015 Board of Mayor and Alderman work session, city staff was directed to change the scope of work to incorporate a 10’ wide multiuse trail along SR96E vs a 5’ sidewalk.  This change significantly increase the cost and scope of the project.  

 

The project has been designed as an open ditch section to help reduce the construction cost and avoid relocation cost associated with overhead utilities.  At this point the design is 95% complete and city staff continues to work with impacted utilities to include Atoms Gas, MTEMC, AT&T and Comcast.  Utility Coordination should be completed in January.  Below is an updated project schedule:

 

Task

Planned Start Date

Planned Finish Date

Public Meeting

December 2015

December 2015

ROW Acquisition

January 2016

May 2016

Bid Construction Project*

June 2016

June 2016

BOMA Award Contract*

July 2016

July 2016

Construction*

August 2016

November 2016

* This schedule is contingent upon staff being able to obtain 30 easement prior to June of 2016. 

 

 

Financial Impact

$      48,279.00                                          Design and Survey Cost

$    244,532.47                                          Estimated ROW Cost

$1,303,055.00                                          Estimated Construction Cost

                     $ 93,760.00 - Estimated Sanitary Sewer Relocation Cost

                     $ 18,000.00 - Estimated Water Relocation Cost

                     $170,265.00 - Estimated Stormwater Infrastructure Cost

                     $1,021,030.00                     - Estimated Sidewalk Construction Cost

$TBD                                                               Utility Relocation Cost (Atmos, MTEMC, AT&T, Comcast)

$1,595,866.47                                          Total Estimated Project Cost

 

It should be noted that staff has submitted an application to the Nashville Area MPO to obtain a TDOT Multimodal Access Grant.  The anticipated award date for this grant is in the spring of 2016.  If awarded this grant we could receive up to $1,000,000 of grant funding for the project.  This type of grant would delay project completion in order to go through the federal/state approval process.

 

Recommendation

Staff recommends moving forward with a final public meeting prior to authorizing right-of-way acquisition and construction.