File #: 15-0359    Version: 1 Name:
Type: Presentation Status: Agenda Ready
File created: 4/1/2015 In control: Capital Investment Committee
On agenda: 4/23/2015 Final action: 4/23/2015
Title: Discussion of the Sidewalk Project on the North Side of Hwy 96 East
Attachments: 1. Hwy 96 East Sidewalk Discussion Exhibit A & B 3-19-15.pdf
DATE:                  April 1, 2015
 
TO:            Board of Mayor and Aldermen
 
FROM:            Eric Stuckey, City Administrator
David Parker, P.E., CIP Executive
Paul Holzen, P.E., Director of Engineering
            
SUBJECT:            
title
Discussion of the Sidewalk Project on the North Side of Hwy 96 East
body
 
Purpose
The purpose of this memorandum is to provide the Board of Mayor and Aldermen (BOMA) with information to consider funding for a sidewalk on the north side of Hwy 96 East.
 
Background
As part of Resolution 2014-13, A Resolution to Adopt the Funding Plan for the FYI 2014-2018 CIP (Capital Investment Program) the Board approved $550,300 for a sidewalk project from Pinkerton Park to Mack Hatcher Parkway along HWY 96 E.  On 2/19/2015 and 3/4/2015 a public hearing was held to obtain feedback from the local residents and the general public.  The project was well supported by the residents with the majority of people in favor of the project.  The residents have requested consideration of the following items:
 
1)      Replace the sidewalk with a multi-use trail to accommodate pedestrians and bicycles.
2)      Add bike lanes to both sides of the roadway.
3)      Add streetscape elements to the project.
 
The cost associated with adding bike lanes and streetscape elements into the project would significantly increase the scope and cost associated with this project.  Staff does not support these requests due to the financial impact it would have on the project.
 
In addition to the items above, staff needs to obtain direction from the Board of Mayor and Aldermen to determine the final typical section and sidewalk alignment.  
 
Sidewalk Typical Section Options:
 
Option 1: Curb and gutter section with a 6' grass strip and a 5' sidewalk along the frontage of HWY 96 East.  This would require the relocation of approximately 12 MTEMC utility poles and significantly complicate the project.  (See Exhibit A)
 
Option 2: Curb and gutter section with a 6' grass strip and a 10' multi-use trail along the frontage of HWY 96 East.  This would require the relocation of approximately 17 MTEMC utility poles and significantly increase the cost associated with this project. (See Exhibit A)
 
Option 3: Construct an open ditch section with a 5' sidewalk along HWY 96 East pushing the sidewalk north into private property.  This option would require additional right-of-way acquisition increasing the cost associated with the project but would avoid utility relocations. (See Exhibit A)
 
Option 4: Construct an open ditch section with a 10' multi-use trail along HWY 96 East pushing the sidewalk north into private property.  This option would significantly increase the cost associated with the project, require additional right-of-way acquisition but would avoid utility relocations. (See Exhibit A)
 
Alignment Options:
 
Alignment 1: Construct the sidewalk parallel HWY 96 E along the frontage of Pinkerton Park as shown in purple on Exhibit B.
 
Alignment 2: Construct the sidewalk to connect into Pinkerton Park and not parallel HWY 96 E as shown in red on Exhibit B.
Financial Impact
 
 
Estimated Construction Cost
Estimated Design Cost
Estimated ROW Cost
Total Estimated Cost
Option 1
$600,000
$48,585
$51,700
$700,285
Option 2
$1,025,000
$65,000
$140,000
$1,230,000
Option 3
$680,000
$48,585
$165,000
$893,585
Option 4
$1,105,000
$65,000
$190,000
$1,360,000
Note 1: Add approximately $50,000 to the Total Estimated Construction cost for Alignment 1
Note 2: This estimate assumes the City would not be responsible for utility relocations.
 
Recommendation
No Recommendation at this time.  Staff is seeking input from the Board of Mayor and Aldermen to complete the design.  A formal Resolution will be presented to the Board of Mayor and Aldermen at a future meeting.