File #: 16-0116    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 1/14/2016 In control: Board of Mayor & Aldermen
On agenda: 2/9/2016 Final action: 2/9/2016
Title: Consideration of Amendment No. 2 to the Professional Services Agreement (COF Contract No. 2013-0034) with CDM Smith, Inc. for the Mack Hatcher Extension Project (SR-397 Mack Hatcher Parkway West, from South of SR-96, West of Franklin, to East of SR-106 (US-431), North of Franklin, Williamson County) at a Cost INCREASE of $81,607.00 (01/28/16 CIC 4-0)
Sponsors: Engineering
Attachments: 1. COF 2013-0034 – Amendment 2 Mack Hatcher Extension Project - LA.pdf

 

DATE:                                                               January 28, 2016

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, Director of Engineering

                                          Jonathan Marston, Staff Engineer 3

                                          

SUBJECT:                                          

title

Consideration of Amendment No. 2 to the Professional Services Agreement (COF Contract No. 2013-0034) with CDM Smith, Inc. for the Mack Hatcher Extension Project (SR-397 Mack Hatcher Parkway West, from South of SR-96, West of Franklin, to East of SR-106 (US-431), North of Franklin, Williamson County) at a Cost INCREASE of $81,607.00 (01/28/16 CIC 4-0)

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Amendment No. 2 to the Professional Services Agreement (PSA) (COF Contract No. 2013-0034) with CDM Smith, Inc. for the Mack Hatcher Extension Project (SR-397 Mack Hatcher Parkway West, from South of SR-96, West of Franklin, to East of SR-106 (US-431), North of Franklin, Williamson County)

 

Background

A brief history of the PSA (COF Contract No. 2013-0034) with CDM Smith, Inc. is as follows:

 

April 23, 2013                     BOMA approved COF Contract No. 2013-0034 that, at the request of TDOT, allowed for the redesign of the proposed roundabouts to traditional signalized intersections.

 

November 25, 2014                     BOMA approved Amendment No. 1 that, at the request of TDOT, allowed for the redesign of the project as a two (2) lane facility.

 

Amendment No. 4, as requested by TDOT, provides the following design revisions: addition of a permanent access easement, plans revision to show more controlled access right-of-way, inclusion of more raised medians at Hillsboro Road (SR-106/US-431), elimination of the micropile design alternate for the Harpeth River Bridge pier footings, and additional information about the retaining walls on the project.

 

Financial Impact

The estimated cost of the design revisions associated with Amendment No. 2 is $81,607.00.  Per proposed Amendment No. 4 to TDOT Contract No. 070112 (COF Contract No. 2009-0051), 100% of these costs will be reimbursed by TDOT.

 

Recommendation

rec

Staff recommends approval of Amendment No. 2 to the PSA (COF Contract No. 2013-0034) with CDM Smith, Inc.