DATE:                                                               May 26, 2016

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, Director of Engineering                     

                                          

SUBJECT:                                          

title

Stormwater Projects Status Report

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City’s stormwater projects.

 

Project Status

 

A.                     100-Block Battle Avenue Drainage Improvements

Key Dates: Design Start - July 24, 2012 (BOMA Approved); Design Completion - January 2016*; Easement Acquisition Start - June 2016*; Easement Acquisition Completion - November 2016*; Bid Date - January 2017*; Construction Start - April 2017*; Construction Completion - August 2017*

*Denotes Estimated Dates                     

Cost: Initial Study - $46,500.00; Final Design - $131,700.00 (Including Amendment 1 of $68,200.00); Construction Estimate- $1,200,000.00

Status Update:  Geotechnical explorations were completed at the end of September.  The final design will continue into spring/summer 2016.  ROW Acquisition could begin in early summer 2016.  Staff and the design consultant are currently evaluating design changes based upon the recent geotechnical data.  The depth of bedrock could hamper the depth of the proposed detention pond. 

 

B.                     Figuers Drive and 400-Block Battle Avenue Drainage Improvements

Key Dates: Design Start - November 26, 2013 (BOMA Approved); Design Completion for Preliminary Design- November 2014; Easement Acquisition Start - TBD; Easement Acquisition Completion - TBD; Bid Date - TBD; Construction Start - TBD; Construction Completion - TBD;

Cost: Initial Design - $82,000.00; Final Design - $125,200.00; Construction - TBD (engineering estimate)

Status Update:  Final Design field survey was completed in November 2015.  Final design began in December 2015, and will continue into the spring and summer of 2016.   

 

C.                     Ralston Creek (Cheswicke Farms) Stream Restoration

Key Dates: Design Start - July 2013; Design Completion - December 2014; Bid Date - January 13, 2015; Construction Start - August 24, 2015; Construction Completion - October 23, 2015

Cost: Design - $57,050.00; Construction - $89,061.00 (bid amount)

Status Update:  Construction is complete and the contractor recently finished installation of landscaping materials.  A final change order should appear on an upcoming agenda.