File #: 15-0169    Version: 1 Name: Discussion of Sidewalk / Trail along New Hwy 96 west
Type: Presentation Status: Agenda Ready
File created: 1/28/2015 In control: Capital Investment Committee
On agenda: 2/5/2015 Final action:
Title: es Discussion of the Sidewalk/Multiuse Trail Project along the north side of New Highway 96 West (SR-96W) and the Sidewalk Project along the north side of Murfreesboro Road (SR-96)
Sponsors: Engineering
Attachments: 1. Hwy 96 Sidewalk Discussion.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
 
DATE:                  January 28, 2015
 
TO:            Board of Mayor and Aldermen
 
FROM:            Eric Stuckey, City Administrator
            David Parker, City Engineering/CIP Executive
            Paul Holzen, Director of Engineering      
            
SUBJECT:            
titlees
Discussion of the Sidewalk/Multiuse Trail Project along the north side of New Highway 96 West (SR-96W) and the Sidewalk Project along the north side of Murfreesboro Road (SR-96)
body
 
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning funding for sidewalk or multiuse trail along the north side of New Highway 96 West (SR-96W) and sidewalk along the north side of Murfreesboro Road (SR-96).
 
Background
As part of Resolution 2014-13, A Resolution to Adopt the Funding Plan for the FYI 2014-2018 CIP (Capital Investment Program), the Board approved $108,220 for a sidewalk project from Vera Valley Drive to the intersection of Downs Boulevard along New Highway 96 West (SR-96W) and $550,300 for a sidewalk project along Murfreesboro Road (SR-96), from Pinkerton Park to Mack Hatcher Parkway.  At this point, the design for the New Highway 96 West multiuse trail is 100% complete and ready for permits; the sidewalk design for Murfreesboro Road is also nearing completion.  Below is a breakdown of the estimated cost:
 
HWY 96W Sidewalk Project
 
5' Sidewalk
Multiuse Trail
Vera Valley Dr to Downs Blvd
$253,000
$293,000
Downs Blvd to Vintage Grove Ln
$290,000
$340,000
Total Estimated Cost
$543,000
$633,000
 
HWY 96E Sidewalk Project
 
5' Sidewalk
Pinkerton Park to Mack Hatcher Pkwy
$650,000
 
Financial Impact
The BOMA approved $150,000 for improvements to Aspen Grove Drive & Seaboard Lane and $250,000 for signal upgrades along Murfreesboro Road (SR-96) as a part of the FY 2014-2015 TOC Budget.  These funds could be shifted to the sidewalk projects to help fund the BOMA's priority projects.  Below is a breakdown of available funding.
 
$   150,000 from the approved 2013-2014 TOC Budget (89530 Machinery & Equipment >$25,000)
$   250,000 from the approved 2013-2014 TOC Budget (89530 Machinery & Equipment >$25,000)
$   108,220 from the approved FYI 2014-2018 CIP Budget (Resolution 2014-13)
$   550,300 from the approved FYI 2014-2018 CIP Budget (Resolution 2014-13)
$1,058,520 Total Available Funds
 
Recommendation
rec
Staff recommends bidding out the New Highway 96 West (SR-96W) Project as a multiuse trail, from Vera Valley Drive to Vintage Grove Lane, and the Murfreesboro Road (SR-96) Sidewalk Project, from Pinkerton Park to Mack Hatcher Parkway.  The total estimated cost is $1,283,000.