File #: 16-0161    Version: 1 Name: SR96 Sidewalk Project (Pinkerton Park to MH Pkwy)
Type: Report Status: Agenda Ready
File created: 1/29/2016 In control: Work Session
On agenda: 2/9/2016 Final action:
Title: Discussion concerning the SR96 East Sidewalk Project (Pinkerton Park to Mack Hatcher Parkway Project)
Sponsors: Paul Holzen
Attachments: 1. 1-27-2016 PUBLIC MEETING EXHIBITS2

 

DATE:                                                               January 29, 2016

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

Paul Holzen, Director of Engineering

                                                               Jonathan Marston, Staff Engineer III

 

SUBJECT:                                          

title

Discussion concerning the SR96 East Sidewalk Project (Pinkerton Park to Mack Hatcher Parkway Project)

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the SR96 East Sidewalk Project, from Pinkerton Park to Mack Hatcher Parkway.

 

Background

As part of Resolution 2014-13, A Resolution to Adopt the Funding Plan for the FYI 2014-2018 CIP (Capital Investment Program), the BOMA approved $550,300 for a sidewalk project along Murfreesboro Road (SR-96), from Pinkerton Park to Mack Hatcher Parkway (SR-397).  On February 19, 2015 and March 4, 2015, public hearings were held to obtain feedback from the local residents and the general public.  The project was well supported by the residents with the majority of people in favor of the project.  The main takeaways from those meetings were:

 

1)                     Request to provide accommodation for bicycles.

2)                     Request to add streetscape elements to the project.

 

After discussing these issues with the BOMA, it was determined to revise the project from a five (5) foot sidewalk to a ten (10) foot multi-use trail.  Design of the project with curb and gutter versus an open ditch was also discussed.  Ultimately, due to the required relocation of multiple overhead utilities with a curb and gutter section, the BOMA decided to proceed with an open ditch design.  These changes increased the project cost to approximately $1,360,000.   Staff was not directed to add bike lanes and streetscape elements to the project. 

 

On January 27, 2016 a third public meeting was held to present and to obtain additional feedback on the revised final design.  This meeting was well attended, with many questions from the public.  The response from the public was split between a five (5) foot sidewalk and the ten (10) foot multi-use trail.  Property owners, who would be directly impacted by project construction, generally favored the five (5) foot sidewalk.  There were also requests for a limited streetscape elements (e.g. decorative lighting) with the project.  City staff is seeking BOMA direction on this project.  Any major changes to the design could result in a six (6) month delay to the project.  Below is a project schedule, assuming the BOMA approves the current project, a ten (10) foot multi-use trail with open ditch drainage.

 

Project Schedule

April 2016                                          Start Right-of-Way (ROW) Acquisition

August 2016                                          Finalize ROW Acquisition

September 2016                     Advertise Bids

November 2016                     BOMA to award Bids

Spring 2017                                          Start Construction (Estimated at 4 Months)

 

Recommendation

The purpose of this item is to follow-up on the recent public meeting regarding the 96 East Sidewalk/Multi-use Trail project.  Staff seeks direction from the Board regarding any modification to the earlier decision to construct a 10-foot multi-use path along 96 East from Pinkerton Park to Mack Hatcher Parkway.