DATE: May 28, 2015
TO: Board of Mayor and Aldermen
FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Mark Hilty, Director of Water Management
Paul Holzen, Director of Engineering
SUBJECT:
title
Water and Sewer Projects Status Report
body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's water and sewer projects.
Projects Status
A. 11th Avenue Improvements
Key Dates: Design Start - January 22, 2013; Design Completion - July 2013; Easement Acquisition Start - November 2013; Easement Acquisition Completion - January 2014; Bid Date: November 25, 2013; Construction Start - May 2014; Construction Completion - November 2014 (March 2015 for Sidewalks)
Cost: Design - $47,232.00; Construction - $700,846.89
Funding Source: Design - Water and Sewer Operating; Construction - Water & Sewer Fund
Status Update: The final change order is on the agenda for approval at the May 2015 CIC meeting.
B. Spencer Creek Basin - South Prong Interceptor Upgrade
Key Dates: Design Start - April 23, 2013; Design Completion - June 2015*; Bid Date: Not Funded; Construction Start - Not Funded; Construction Completion - Not Funded
*Denotes Estimated Date
Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded
Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD
Status Update: Design plans are currently in the works but the project will not be constructed until the monies are available from the WMD budget.
C. Charlton Green Sanitary Sewer Improvements
Key Dates: Design Start - November 12, 2013; Design Completion - March 2014; Bid Date: April 7, 2014; Construction Start - December 1, 2014; Construction Completion - April 2015
Cost: Design - $19,895.00; Easement - $3,500.00; Construction -$465,304.90
Funding Source: Design -Sewer Operating; Construction - Sewer Fund
Status Update: The contractor has finished the Staff's last punch list and all of the work is complete. The final change order will be on the June 2015 CIC meeting agenda.
D. Spencer Creek at Franklin Road Sewer
Key Dates: Design Start - March 11, 2014; Design Completion - June 2015*; Easement Acquisition Start - May 2015*; Easement Acquisition Completion - July 2015*; Bid Date: August 2015*; Construction Start - October 2015*; Construction Completion - May 2016*
*Denotes Estimated Date
Cost: Design - $40,000.00; Easement - TBD; Construction - TBD
Funding Source: Design - Sewer Fund
Status Update: The SWPPP has been signed and submitted to TDEC for approval. The TDOT permit to cross Franklin Road has been approved. CSX received the permit request on February 20, 2015 and will take between 60 and 90 days to go through the approval process. City Staff and the consultant have met and agreed on the alignment. Easement documents are being drafted.
E. Curd Branch and Watson Branch Interceptor Sewer
Key Dates: Design Start - February 25, 2014; Design Completion - March 2015; Easement Acquisition Start - February 2015; Easement Acquisition Completion - June 2015*; Bid Date: August 2015*; Construction Start - September 2015*; Construction Completion - August 2016*
*Denotes Estimated Date
Cost: Design - $115,000.00; Easement - TBD; Construction - TBD
Funding Source: Design - Sewer Fund
Status Update: Plans have been submitted for approval to TDEC. The easement acquisition process is continuing.
F. Fieldstone Farms Pump Station No. 1 Rehabilitation
Key Dates: Design Start - January 14, 2014; Design Completion - November 2014; Bid Date: December 11, 2014; Construction Start - June 2015*; Construction Completion - June 2016*
*Denotes Estimated Date
Cost: Design - $226,848.00; CEI - $196,000.00; Construction - $1,592,000.00
Funding Source: Design - Sewer Fund; Construction - Sewer Operating Fund
Status Update: The pre-construction meeting will be on May 22, 2015 with work starting around the first part of June 2015.
G. Sanitary Sewer System Model and Capacity Assurance Tool - Phase 1
Key Dates: Design Start - March 11, 2014; Design Completion - April 2015
Cost: Design - $182,000.00
Funding Source: Design - Sewer Fund
Status Update: The engineer is working on completing the data needed to run the model. The tool has been delivered to the City to use.
I. Goose Creek Sanitary Sewer Extension Project from West of I65 to the East Side of I65
Key Dates: Design Start - September 9, 2014; Design Completion - April 2015; Easement Acquisition Start - May 2015*; Easement Acquisition Completion - August 2015*; Bid Date: October 2015*; Construction Start - November 2015*; Construction Completion - June 2016*
*Denotes Estimated Date
Cost: Design - $120,725.00; Easement - TBD; Construction - TBD
Funding Source: Design, Easement, Construction - Sewer Fund & HPT TA Properties Trust
Status Update: Staff has met with the consultant to discuss the design plans prior to submittal to TDEC. Easement documents were reviewed and comments are currently being addressed. The condemnation resolution for the easements was on the April 2015 CIC agenda.