Title: Williamson County Ag Expo Park, Site Plan, ADA Parking addition, creation of 48 accessible parking spaces adjacent to the existing expo building located at 4215 Long Lane (Consent Agenda)
Sponsors: Franklin Municipal Planning Commission, Josh King
Attachments: 1. 6117_AgExpo_Conditions of Approval_01.pdf, 2. map_6117AGExpoCenter.pdf, 3. AG Site Layout.pdf, 4. 2016-05-04 Ag Center ADA Parking Addition Full Set.pdf

 

DATE:                                                               5/18/2016

 

TO:                                          Franklin Municipal Planning Commission

 

FROM:                                          Josh King, Senior Planner

                                          Bob Martin, Interim Director of Planning and Sustainability

 

Subject

title

Williamson County Ag Expo Park, Site Plan, ADA Parking addition, creation of 48 accessible parking spaces adjacent to the existing expo building located at 4215 Long Lane (Consent Agenda)

body

 

Project Information

COF Project Number:                                          6117

Applicant:                                                               Chris Collier, Collier Engineering

Owner:                                                               Williamson County

 

Background/Staff Comments

The applicant is proposing to add 48 accessible parking stalls adjacent to the existing building and barrier free entrance at the Ag Expo Center located at 4215 Long Lane.  The proposed parking lot will be paved and is designed to meet City of Franklin regulations.  The applicant is also adding stormwater features to capture and treat stormwater from the developed area.

 

Recommendation

recommendation

Approval, with conditions. 

end

See attached pages for a list of staff recommended conditions of approval.

 

PROCEDURAL REQUIREMENTS:                     

1.                     The applicant shall upload the corrected plan to the online plan review website (<https://franklin.contractorsplanroom.com/secure/>).  All revisions to the approved plans shall be “clouded.” With the resubmittal, each condition of approval/open issue in the online plan review system shall contain a full response from the applicant as to the satisfaction or completion of that condition.

2.                     Once the corrected site plan has been approved, one (1) full-size and one (1) half-size copy of the final approved landscape plans shall be submitted to the Department of Building and Neighborhood Services for future landscape inspection purposes.

3.                     Once the project has obtained Site Plan approval, the applicant will be notified by COF Engineering Department with instructions regarding the status of their digitally stamped construction plans.

4.                     The applicant shall upload complete building plans, including the approved, revised site plans, to the City's IDT site for Building and Neighborhood Services Department review and approval prior to the issuance of a building permit.

5.                     Prior to start of any excavation work, the developer and/or contractor shall notify AT&T and Comcast.

6.                     The city’s project identification number shall be included on all correspondence with any city department relative to this project.