File #: 18-0687    Version: 1 Name:
Type: Planning Item Status: Passed
File created: 7/2/2018 In control: Franklin Municipal Planning Commission
On agenda: 7/26/2018 Final action: 7/26/2018
Title: Waterford Subdivision, Site Plan, Lot 2, Revision 1, (Columbia State Community College Parking Garage), Construction Of A 3-Story Parking Garage On A 36 Acre Lot, Located At 1228 Liberty Pike. (CONSENT AGENDA)
Sponsors: Franklin Municipal Planning Commission, Josh King
Attachments: 1. MAP_WaterfordCCSCGarage.pdf, 2. CCSCGARAGE_Conditions of Approval_01.pdf, 3. CCSC_Elevations.pdf, 4. Masterplan_CCSC.pdf, 5. COF #6755-CSCC Garage-Resubmittal.pdf

 

DATE:                                                               July 18, 2018

 

TO:                                          Franklin Municipal Planning Commission

 

FROM:                                          Josh King, Principal Planner

                                          Amy Diaz-Barriga, Current Planning Supervisor

                                          Emily Hunter, Director of Planning and Sustainability

 

Subject

title

Waterford Subdivision, Site Plan, Lot 2, Revision 1, (Columbia State Community College Parking Garage), Construction Of A 3-Story Parking Garage On A 36 Acre Lot, Located At 1228 Liberty Pike. (CONSENT AGENDA)                     

body

 

Project Information

COF Project Number:                                          6755

Applicant:                                                               Sara Hooper, Barge Cauthen and Associates

Owner:                                                               State of Tennessee

 

Background/Staff Comments

This site plan is intended for Columbia State Community College (CSCC) to construct a 3-story parking garage.  The garage will be located on the eastside of Knoll Top Lane and the academic quad of the existing buildings.  A master plan for the CSCC complex originally showed a parking lot in this location.

 

Recommendation

recommendation

Approval, with Conditions.

end

See attached pages for a list of staff recommended conditions of approval.

 

PROCEDURAL REQUIREMENTS:                     

1.                     The applicant shall upload the corrected plan to the online plan review website (<https://franklin.contractorsplanroom.com/secure/>).  All revisions to the approved plans shall be “clouded.” With the resubmittal, each condition of approval/open issue in the online plan review system shall contain a full response from the applicant as to the satisfaction or completion of that condition.

2.                     Once the corrected site plan has been approved, one (1) full-size and one (1) half-size copy of the final approved landscape plans shall be submitted to the Department of Building and Neighborhood Services for future landscape inspection purposes.

3.                     Once the project has obtained Site Plan approval, the applicant will be notified by COF Engineering Department with instructions regarding the status of their digitally stamped construction plans.

4.                     The applicant shall upload complete building plans, including the approved, revised site plans, to the City's IDT site for Building and Neighborhood Services Department review and approval prior to the issuance of a building permit.

5.                     Prior to start of any excavation work, the developer and/or contractor shall notify AT&T and Comcast.

6.                     The city’s project identification number shall be included on all correspondence with any city department relative to this project.