File #: 16-0461    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 5/13/2016 In control: Board of Mayor & Aldermen
On agenda: 6/14/2016 Final action: 6/14/2016
Title: Consideration of Change Order No. 1 to the Construction Contract (COF Contract No. 2014-0037, Resolution 2015-46) with Jones Bros. Contractors, LLC for the 3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase I, TDOT PIN 109424.00) (05/26/16 CIC 4-0)
Attachments: 1. COF2014-0037_3rd_Ave_Trail-Change_Order_1_ExhA

 

DATE:                                                               May 13, 2016

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, Director of Engineering

                                          William Banks, Staff Engineer

 

                     

                                          

SUBJECT:                                          

title

Consideration of Change Order No. 1 to the Construction Contract (COF Contract No. 2014-0037, Resolution 2015-46) with Jones Bros. Contractors, LLC for the 3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase I, TDOT PIN 109424.00) (05/26/16 CIC 4-0)

body

 

Purpose

The purpose of this memorandum is to provide information to the City of Franklin Board of Mayor and Aldermen (BOMA) concerning Change Order No. 1 to the construction contract (COF Contract No. 2014-0037, Resolution 2015-46) with Jones Bros. Contractors, LLC for the 3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase I, TDOT PIN 109424.00).

 

Background

The 3rd Avenue North Trail/Greenway (Bicentennial Park Phase I) construction contract was awarded by BOMA to Jones Bros. Contractors, LLC on August 11, 2015, in the amount of $1,253,257.31.  The original contract completion date was scheduled for May 17, 2016 (240 Calendar Days). 

 

This Change Order No. 1 includes small changes required to properly complete the project, and a request for additional time to the construction contract.  Change Order No. 1 details include the following:

1.                     Additional pay items:

a.                     Tree removal to eliminate a conflict with overlook installation. 

b.                     Storm drainage structures to tie into the 3rd Ave N Roadway Project’s storm system. 

c.                     Surge stone required for compaction around water stairs and under the overlook structure to prevent area from washing out when river level rises.  Also, the existing excavated soil did not meet specifications for backfill placement, so it could not be re-used as indicated on the plans. 

2.                     Modify contract time as follows:

a.                     10 additional calendar days due to normal weather delays/impacts (rain, snow, etc.) from September 2015 thru April 2016.     

b.                     65 additional calendar days due to the Harpeth River’s high water levels during the winter months, causing delays in the water stairs and overlook construction.  The original stream diversion was not sufficient for the high water levels encountered during the winter months.  A secondary stream diversion was installed using sheet piling and steel beams in order to provide an area that could be properly de-watered by the contractor. 

c.                     Contract time will increase from 240 Calendar Days to 315 Calendar Days, with a new completion date of July 31, 2016. 

 

See attached Exhibit A for the Change Order No. 1 documentation. 

 

Financial Impact

There is a $100,000.00 contingency amount built in for this construction project per Resolution 2015-46. Change Order No. 1 to the construction contract (COF Contract No. 2014-0037, Resolution 2015-46) with Jones Bros. Contractors, LLC is a contract increase of $32,269.60.  The project contingency will be reduced to cover this cost increase.  This creates a new Contract Price of $1,285,526.91. 

 

Recommendation

Staff recommends approval of Change Order No. 1 to the construction contract (COF Contract No. 2014-0037) with Jones Bros. Contractors, LLC.