DATE: September 24, 2015
TO: Board of Mayor and Aldermen
FROM: Eric Stuckey, City Administrator
David Parker, City Engineer/CIP Executive
Paul Holzen, Director of Engineering
SUBJECT:
title
Transportation Projects Status Report
body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning ENTER PURPOSE the status of some of the City’s transportation projects.
Project Status
A. Mack Hatcher Parkway NW Extension
BOMA Priority Ranking: N/A (Highest Priority)
Key Dates: Design Start - August 14, 2007 (BOMA Approval); Re-Design Completion - January 2015; ROW Start - December 2009; ROW Completion - June 2012; Construction Start - Currently Not Funded; Construction Completion - Currently Not Funded
Cost: Design - $3,502,501; ROW - $13,397,520 (Provided by TDOT); Construction - $58,700,000 (Provided by TDOT)
Status Update: TDOT has agreed to build the full intersections at SR96, Hillsboro Road and Del Rio Pike as a part of the 2-lane Mack Hatcher Parkway construction. On Thursday, April 9TH, the City received notification from the TDOT Communications Office of projects on the Statewide Transportation Improvement Plan (STIP) for the 3-year period from 2016-2018, and this project was not included. A field review of the construction plans was held at TDOT’s Region 3 offices in Nashville, TN on April 16TH. The designer is completing final plans comments, as requested by TDOT.
B. Hillsboro Road Improvements Phase 2 (Independence Square to Mack Hatcher Pkwy)
BOMA Priority Ranking: #1
Key Dates: Design Start - March 24, 2008 (BOMA Approval); Design Completion - March 2015; ROW Start - March 2013; ROW Completion - May 2015; Bid Date - October 2015*; Construction Start - December 2015*; Construction Completion - April 2017*
*Denotes Estimated Date
Cost: Design - $1,324,221 (Design fees include the SR96-IndSq Project as well); ROW - $3,000,000; Construction - $13,217,983.82 ($1,750,000 Reimbursable through State and Federal Approved Funding; Includes AT&T and ATMOS Reimbursable items totaling $590,470.60)
Status Update: Construction Plans were reviewed by TDOT, and returned with comments. Revised plans were submitted to TDOT in August for final approval and authorization to bid the project out.
C. Carothers Parkway South Extension
BOMA Priority Ranking: #5
Key Dates: Design Start - July 10, 2007; Design Completion - March 2013*; ROW Start - May 26, 2009; ROW Completion - March 2011; Bid Date - April 2013; Construction Start - September 1, 2013; Construction Completion - September 2015* (Substantial Completion)
*Denotes Estimated Date
Cost: Design - $2,116,560; ROW - $500,000.00 (Estimated); CEI Services - $1,113,500 (Approved Contract); Construction - $13,292,567.42 (Approved Contract and COs)
Status Update: Project was opened to traffic on September 23, 2015. Crews continue to work on punch list items.
D. Century Court / Beasley Drive Connector
Key Dates: Design Start - May 8, 2007; Design Complete - March 2015*; ROW Start - March 2008; ROW Complete -March 2015*; Bid Date - June 2015; Construction Start - October 2015*; Construction Complete - April 2015*
*Denotes Estimated Date
Cost: Design - $27,526; ROW - $153,450; Construction - $399,250.97 (Bid Amount)
Status Update: Construction bids were received and opened on July 8TH. A resolution for approval of this contract with Jenco Construction was approved at the August 11, 2015 meeting. Middle Tennessee Electric is completed with their relocation, AT&T is in the process of relocating and Comcast will start relocation after AT&T is complete.
E. Hunter’s Bend Safe Routes to School
Key Dates: Design Start- January 2014; Design Complete - May 2014*; ROW Start - N/A; ROW Complete - N/A; Bid Date - August 2015* Construction Start - September 2015*; Construction Complete - November 2015*
*Denotes Estimated Date
Cost: Total - $289,565 (Estimated)
Status Update: Design plans have been submitted by TDOT. Designer has received comments from TDOT and will resubmit. Bidding for construction cannot occur without a Notice to Proceed from TDOT; the City is awaiting this notice. As soon as this Notice to Proceed is issued by TDOT, we can proceed with bidding and construction.
F. Multiuse Trail along Highway 96 West, Vintage Grove Lane to Freedom Middle School
Key Dates: Design Start- June 2014; Design Complete - September 2014; ROW Start - March 2015; ROW Complete - July 2015*; Bid Date - July 2015; Construction Start - October 2015*; Construction Complete - January 2015*
*Denotes Estimated Date
Cost: Construction - $596,116.10 (Bid Amount)
Status Update: Construction bids were received and opened on July 8TH. Construction bids were received and opened on July 8TH. A resolution for approval of this contract with Civil Constructors, LLC was approved at the August 11, 2015 meeting. Negotiations for easement are underway. Work will begin once the easement acquisition process is complete.
G. Sidewalk along Murfreesboro Road (SR 96 East), Pinkerton Park to Mack Hatcher Parkway
Key Dates: Design Start- June 2014; Design Complete*; December 2014; ROW Start* - February 2016*; ROW Complete* - June 2016; Bid Date* - July 2016; Construction Start* - September 2016; Construction Complete* - November 2016
*Denotes Estimated Date
Cost: Total - $1,360,000
Status Update: City Staff is currently updating the design plans to show a multi-use trail, as requested by the public and as directed by the BOMA.
H. Franklin Road (Harpeth River Bridge to Harpeth Industrial Court)
Key Dates: Design Start- January 2015; Design Complete - January 2016*;
ROW Acquisition- Not Funded; Construction - Not Funded
*Denotes Estimated Date
Cost: Total - $10,344,250 (Estimated)
Status Update: Final Design PSA was approved by BOMA on October 14, 2014. The survey update is complete. Design updates are ongoing. A Utility Coordination Meeting was held on July 22nd. Water and Sanitary Sewer design contracts are being reviewed by Law, and hopefully will go to the BOMA in October for approval.
I. 3rd Avenue North Trail/Greenway Project (Bicentennial Park Phase 1)
Key Dates: Design Start - April 11, 2006; Design Completion - February 2013; ROW Start - October 9, 2007; ROW Completion - January 26, 2010; Bid Dates - July 8, 2015; Construction Start - October 2015*; Construction Completion - July 2016*
*Denotes Estimated Date
Cost: Design - $65,725.00 (This number does not include design cost from the Bicentennial Park Project); ROW - $226,500.00; Construction - $1,253,257.31 (Bid Amount)
Status Update: TDOT concurred with low bidder recommendation. The bid was awarded to Jones Bros Contractors, LLC on August 11, 2015. Notice to proceed will be issued in September.
J. East McEwen Drive Phase 4 Improvements
Key Dates: Design Start - April 2015; Design Completion - April 2016*; ROW Acquisition - Not Funded; Construction - Not Funded
*Denotes Estimated Date
Cost: Design - $1,210,000 (Preliminary - $497,000; Final - $713,000); ROW - Not Funded; Construction - Not Funded
Status Update: The PSA for final design (COF Contract No. 2015-0052) was approved by the BOMA at their March 24TH meeting. Design work continues.
K. Columbia Avenue (Mack Hatcher Parkway to Downs Boulevard)
Key Dates & Cost: TBD upon final approval of Local Agency Project Agreement between TDOT and the City of Franklin, and bringing the engineering consultant on board.
Cost: TBD (current total estimate is $21M)
Status Update: On July 8TH, the City received 16 proposals and letters of interest from engineering consultants. Staff have reviewed the 16 proposals and invited the top 5 scoring firms to in-person interviews on September 14TH and 15TH. TDOT’s Local Programs Development Office approved the funding agreement with the City (80% Federal / 20% State / 0% Local funding), and issued the Notice to Proceed with Preliminary Engineering. As soon as a PSA has been approved with the selected consultant, preliminary design can begin.