Skip to main content
File #: 15-0658    Version: 1 Name:
Type: Report Status: Passed
File created: 7/13/2015 In control: Capital Investment Committee
On agenda: 7/23/2015 Final action: 7/23/2015
Title: Water and Sewer Projects Status Report
Sponsors: Engineering

 

DATE:                                                               July 23, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          David Parker, City Engineer/CIP Executive

                                          Paul Holzen, Director of Engineering                     

                                          

SUBJECT:                                          

title

Water and Sewer Projects Status Report

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City’s water and sewer projects.

 

Project Status

rec

 

A.                     Spencer Creek Basin - South Prong Interceptor Upgrade

Key Dates: Design Start - April 23, 2013; Design Completion - June 2015*; Bid Date: Not Funded; Construction Start - Not Funded; Construction Completion - Not Funded

*Denotes Estimated Date

Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded

Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD

Status Update:  Design plans are currently underway and are approximately 50% complete.  Staff and the engineer met in the field to discuss how to route the sewer through Aspen Grove Park.  The project will not be constructed until funding is available from the Water Management Department budget.

 

B.                     Charlton Green Sanitary Sewer Improvements

Key Dates: Design Start - November 12, 2013; Design Completion - March 2014; Bid Date:  April 7, 2014; Construction Start - December 1, 2014; Construction Completion - April 2015

Cost: Design - $19,895.00; Easement - $3,500.00; Construction -$465,304.90

Funding Source: Design -Sewer Operating; Construction - Sewer Fund

Status Update:  The final change order is on the July 2015 Board of Mayor and Aldermen meeting agenda for approval.

 

C.                     Spencer Creek at Franklin Road Sewer

Key Dates: Design Start - March 11, 2014; Design Completion - June 2015; Easement Acquisition Start - July 2015*; Easement Acquisition Completion - September 2015*; Bid Date: October 2015*; Construction Start - December 2015*; Construction Completion - May 2016*

                     *Denotes Estimated Date

Cost: Design - $40,000.00; Easement - TBD; Construction - TBD

Funding Source: Design - Sewer Fund

Status Update:    The CSX permit package is on the July 2015 CIC agenda.  Design plans are 100% complete but plans will not be submitted to TDEC for approval until the easements are obtained.  Negotiations with the property owners has begun. 

 

D.                     Curd Branch and Watson Branch Interceptor Sewer

Key Dates: Design Start - February 25, 2014; Design Completion - March 2015; Easement Acquisition Start - February 2015; Easement Acquisition Completion - July 2015*; Bid Date: August 2015*; Construction Start - September 2015*; Construction Completion - August 2016*

*Denotes Estimated Date

Cost: Design - $115,000.00; Easement - TBD; Construction - TBD

Funding Source: Design - Sewer Fund

Status Update:  The easement acquisition process is continuing.  Design plans are 100% complete but plans will not be submitted to TDEC for approval until the easements are obtained.

 

E.                     Fieldstone Farms Pump Station No. 1 Rehabilitation

Key Dates: Design Start - January 14, 2014; Design Completion - November 2014; Bid Date: December 11, 2014; Construction Start - July 2015*; Construction Completion - July 2016*

*Denotes Estimated Date

Cost: Design - $226,848.00; CEI - $196,000.00; Construction - $1,592,000.00

Funding Source: Design - Sewer Fund; Construction - Sewer Operating Fund

Status Update:  Staff, engineering consultant and contractor are meeting July 14th to go over status of submittals and job scheduling.

 

F.                     Sanitary Sewer System Model and Capacity Assurance Tool - Phase 1

Key Dates: Design Start - March 11, 2014; Design Completion - April 2015

Cost: Design - $182,000.00

Funding Source: Design - Sewer Fund

Status Update:  The data needed to run the model has been completed.  Staff and the engineer are going to meet in the next couple of weeks to go over the tool again now that the data has been completed.  

 

G.                     Goose Creek Sanitary Sewer Extension Project from West of I65 to the East Side of I65

Key Dates: Design Start - September 9, 2014; Design Completion - April 2015; Easement Acquisition Start - July 2015*; Easement Acquisition Completion - September 2015*; Bid Date: November 2015*; Construction Start - January 2016*; Construction Completion - July 2016*

*Denotes Estimated Date

Cost: Design - $120,725.00; Easement - TBD; Construction - TBD

Funding Source: Design, Easement, Construction - Sewer Fund & HPT TA Properties Trust

Status Update:  Staff requested that reclaimed water be added to this project.  The consultant is working on making revisions to the plans and easements to reflect this request.