File #: 15-0633    Version: 1 Name:
Type: Planning Item Status: Passed
File created: 7/10/2015 In control: Franklin Municipal Planning Commission
On agenda: 7/23/2015 Final action: 7/23/2015
Title: Highlands at Ladd Park PUD Subdivision, final plat, section 25, revision 1, 25 detached residential lots and two open-space lots on 20.71 acres, located along Ryecroft Lane. (CONSENT AGENDA)
Attachments: 1. MAP, 2. Conditions of Approval, 3. Final Plat

 

DATE:                                                               July 15, 2015

 

TO:                                          Franklin Municipal Planning Commission

 

FROM:                                          Andrew Orr, Principal Planner

                                          Bob Martin, Interim Director of Planning and Sustainability

 

Subject

title

Highlands at Ladd Park PUD Subdivision, final plat, section 25, revision 1, 25 detached residential lots and two open-space lots on 20.71 acres, located along Ryecroft Lane. (CONSENT AGENDA)                     

body

 

Project Information

COF Project Number:  5864

Applicant:  David Reagan, HFR Design

Owner:  Paul Arnold, TEADEAN LP; John Hughey, Propst Nashville LLC

 

Background/Staff Comments

The property is zoned R-2. The first plat for this section was approved on May 20, 2015, by the Planning Commission (project number 5826). The corresponding site plan (project number 4696) was approved administratively on November 14, 2015. The site plan was approved for 66 detached single family homes and four open-space lots. The applicant has been working through the LOMR process in order to plat new lots. 

 

Recommendation

recommendation

Approval, with conditions. 

end

See attached pages for a list of staff recommended conditions of approval.

 

PROCEDURAL REQUIREMENTS:                     

1.                     In addition to uploading the corrected plat to the online plan review website (https://franklin.contractorsplanroom.com/secure/), the applicant shall submit three (3) paper copies and a .pdf file of the corrected plat, along with the Mylar, to the Department of Building and Neighborhood Services (Suite 110, Franklin City Hall). The Certificates of Approval for the Subdivision Name and Street Names, Water System (if not COF Water), Survey, and Ownership shall be signed when the plat is resubmitted. The Mylar shall be submitted to BNS within five (5) business days of the corrected electronic plat being uploaded to the online plan review website (or vice versa) or the item shall be rejected as incomplete for City review.  With the resubmittal, each condition of approval/open issue in the online plan review system shall contain a full response from the applicant as to the satisfaction or completion of that condition.

2.                     The city’s project identification number shall be included on all correspondence with any city department relative to this project.

3.                     The applicant shall upload a .dwg copy of the final plat through the IDT system (link above) in Tennessee state plan coordinates, NAD 83, NAVD 88, zone 4100/5301 for incorporation of the plat into the Franklin GIS database.