File #: 19-0689    Version: 1 Name: Southbrooke Road Impact Offset
Type: Contract/Agreement Status: Passed
File created: 6/24/2019 In control: Board of Mayor & Aldermen
On agenda: 11/12/2019 Final action: 11/12/2019
Title: Consideration of Road Impact Fee Offset Agreement (COF 2019-0221) for the Southbrooke PUD Subdivision with Southbrooke, LLC (WS 7/9/19; BOMA 8/13/19 deferred to 11/12/19) (REQUEST TO WITHDRAW BY APPLICANT)
Sponsors: Paul Holzen, Jimmy Wiseman
Attachments: 1. COF 2019-0221 Road Impact Fee Offset Agreement with Southbrooke LLC_with exhibit_Law Approved 3.pdf

 

DATE:                                                               July 2, 2019

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Jimmy Wiseman, Assistant Director of Engineering

                                          Paul Holzen, Director of Engineering

                                          

SUBJECT:                                          

title

Consideration of Road Impact Fee Offset Agreement (COF 2019-0221) for the Southbrooke PUD Subdivision with Southbrooke, LLC (WS 7/9/19; BOMA 8/13/19 deferred to 11/12/19) (REQUEST TO WITHDRAW BY APPLICANT)   

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning COF 2019-0221 Road Impact Fee Offset Agreement with Southbrooke, LLC

 

Background

As part of the Southbrooke PUD Subdivision, the developer is required to install the following improvements:

 

                     Lewisburg Pike and Goose Creek Bypass:

o                     Provide dual northbound right turn lanes and dual northbound thru lanes on Lewisburg Pike.

o                     Provide dual westbound left turn lanes, a westbound thru lane and a dedicated westbound right turn lane on Goose Creek Bypass as well as a southbound receiving lane on Lewisburg Pike.  The receiving lane shall be designed to accommodate the peak volume needed to prevent delay in the intersection.

o                     Provide dual southbound thru lanes on Lewisburg Pike.

 

                     Provide an east/west minor collector roadway stub from Lewisburg Pike to line up with the future McLemore connection.

Financial Impact

The total eligible costs of design, right-of- way acquisition, easement acquisition, permits, and construction of the above arterial roadway Improvements is (Two Million Nine Hundred Seventy Four Thousand Nine Hundred Thirty and 00/100) ($ 2,974,930.00) for  the  Development  Project  and  the  total  reimbursement  to  the  Developer  is  estimated  to  be ( Two Million Nine Hundred Seventy Four Thousand Nine Hundred Thirty and 00/100)  ( $2,974,930.00).   At   no time shall reimbursement exceed the arterial impact fees collected as part of the Development Project.

Recommendation

rec

Staff recommends approval of COF 2019-0221 Road Impact Fee Offset Agreement for the Southbrooke PUD Subdivision with Southbrooke, LLC.